A project manager who takes over halfway through a project determines that the cost performance index (CPI) is 0.65. A detailed audit identifies that the project cost was analogously estimated, and the audit team thinks that something was missing in the way the estimates were done.
What should have been done to avoid this problem?
cb4a6c4
Highly Voted 9 months, 3 weeks agojanojano
Most Recent 8 months, 2 weeks agoced45c8
8 months, 2 weeks agoKim222
3 weeks, 2 days agoxcjxcj
8 months, 2 weeks agoTrytrio
7 months, 3 weeks agoAbdelmonm
8 months, 3 weeks agoHanbyul
9 months, 3 weeks ago