A project manager who takes over halfway through a project determines that the cost performance index (CPI) is 0.65. A detailed audit identifies that the project cost was analogously estimated, and the audit team thinks that something was missing in the way the estimates were done.
What should have been done to avoid this problem?
cb4a6c4
Highly Voted 11 months, 3 weeks agovictory108
Most Recent 1 month agojanojano
10 months, 2 weeks agoced45c8
10 months, 3 weeks agoKim222
2 months, 3 weeks agoxcjxcj
10 months, 3 weeks agoTrytrio
9 months, 3 weeks agoAbdelmonm
10 months, 3 weeks agoHanbyul
11 months, 4 weeks ago