Welcome to ExamTopics
ExamTopics Logo
- Expert Verified, Online, Free.
exam questions

Exam PMP All Questions

View all questions & answers for the PMP exam

Exam PMP topic 1 question 1046 discussion

Actual exam question from PMI's PMP
Question #: 1046
Topic #: 1
[All PMP Questions]

A project manager who takes over halfway through a project determines that the cost performance index (CPI) is 0.65. A detailed audit identifies that the project cost was analogously estimated, and the audit team thinks that something was missing in the way the estimates were done.

What should have been done to avoid this problem?

  • A. Utilized three-point estimates
  • B. Validated the schedule performance index (SPI) to evaluate deviation
  • C. Included lessons learned from past projects
  • D. Used bottom-up estimating
Show Suggested Answer Hide Answer
Suggested Answer: D 🗳️

Comments

Chosen Answer:
This is a voting comment (?) , you can switch to a simple comment.
Switch to a voting comment New
cb4a6c4
Highly Voted 11 months, 3 weeks ago
Selected Answer: D
Its question about cost, D seems to be the answer.
upvoted 6 times
...
victory108
Most Recent 1 month ago
Selected Answer: D
D. Used bottom-up estimating
upvoted 1 times
...
janojano
10 months, 2 weeks ago
Selected Answer: D
If details were missing, a more thorough estimate should have been used and that would be bottom-up, which examines the work at the most granular level of detail.
upvoted 2 times
...
ced45c8
10 months, 3 weeks ago
Selected Answer: C
please stop using chatGPT, bottom-up is using when we have details cost, does it mentioned in the question? the question is audit team thinks that something is missing, analogous estimation uses historical data from a similar activity or project
upvoted 2 times
Kim222
2 months, 3 weeks ago
It is clear D :)
upvoted 1 times
...
xcjxcj
10 months, 3 weeks ago
The audit found that analogous is not appropriate, this project is different from previous, thus D should be correct.
upvoted 2 times
Trytrio
9 months, 3 weeks ago
Exactly D is correct - please do not stop using ChatGPT ;)
upvoted 1 times
...
...
...
Abdelmonm
10 months, 3 weeks ago
Selected Answer: D
Bottom-up estimating involves estimating the cost or duration of individual work items and then aggregating them to get an overall project estimate. This approach is more detailed and accurate compared to analogous estimating, especially when there might be missing details in the estimates. By breaking down the project into smaller components and estimating each one separately, a more accurate and reliable cost estimate can be obtained. This method is particularly useful when there is uncertainty or complexity in the project. Utilizing three-point estimates and including lessons learned from past projects can also contribute to better estimating accuracy.
upvoted 1 times
...
Hanbyul
11 months, 4 weeks ago
Selected Answer: B
B. Validated the schedule performance index (SPI) to evaluate deviation
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...