A project manager is working on an agile project. The organization decided to implement the Scrum framework. The project manager organized a workshop to explain the differences between traditional project artifacts and the Scrum approach. The most frequent question raised is what artifact will replace the project schedule.
What should be the project manager’s response?
kaarenn
2 weeks, 3 days agovictory108
3 weeks, 5 days agoc8ee0e6
4 months, 2 weeks agoUppersquareCapital
6 months agolatigo
6 months, 1 week agosidje
6 months, 1 week agoompk
6 months, 2 weeks agoAzureFreak
8 months agodimo475
8 months, 1 week agoEfaChux
8 months, 1 week agoDavard
9 months, 3 weeks agoKennyMuffins
9 months, 3 weeks agoTrytrio
9 months, 3 weeks agoDelab202
10 months, 1 week agoAbdelmonm
10 months, 2 weeks agoced45c8
10 months, 2 weeks agokevzzz
10 months, 3 weeks ago