Welcome to ExamTopics
ExamTopics Logo
- Expert Verified, Online, Free.
exam questions

Exam PMP All Questions

View all questions & answers for the PMP exam

Exam PMP topic 1 question 1063 discussion

Actual exam question from PMI's PMP
Question #: 1063
Topic #: 1
[All PMP Questions]

A project manager is transitioning from a predictive life cycle project to a new agile project. How should the project manager manage and control the scope for the new project?

  • A. Estimate the work the team can complete and define story sizes to keep the project under control
  • B. Spend a short amount of time defining the scope and building prototypes to refine the requirements
  • C. Develop a plan to complete more work in less time
  • D. Create a scope baseline and put the rest as backlog activities
Show Suggested Answer Hide Answer
Suggested Answer: A 🗳️

Comments

Chosen Answer:
This is a voting comment (?) , you can switch to a simple comment.
Switch to a voting comment New
Amirov
3 weeks, 2 days ago
Selected Answer: B
gonna go with B
upvoted 2 times
...
23169fd
4 weeks, 1 day ago
Selected Answer: A
In agile, there is no traditional scope baseline like in predictive projects. Instead, the product backlog serves as a dynamic list of prioritized features and requirements, which can be updated based on new information, changing priorities, or customer feedback. The focus is on continuous backlog refinement rather than locking down a scope baseline.
upvoted 1 times
...
victory108
1 month ago
Selected Answer: B
B. Spend a short amount of time defining the scope and building prototypes to refine the requirements
upvoted 1 times
...
27b2ada
2 months, 2 weeks ago
Selected Answer: C
i go with c
upvoted 1 times
...
Kim222
2 months, 3 weeks ago
Selected Answer: D
This is D. PM establishes the scope baseline, conducts a Sprint Planning Meeting, and after the Sprint Backlog, team members determine the story size.
upvoted 1 times
Kim222
2 months, 3 weeks ago
This explanation is meant to proceed in order.
upvoted 1 times
...
...
que1010
4 months, 2 weeks ago
Selected Answer: D
"transitioning from a predictive life cycle project to a new agile project" might need the hybrid approach
upvoted 1 times
...
Trytrio
9 months, 3 weeks ago
Selected Answer: D
Option A focuses on estimating and defining story sizes to control scope, which is a valid agile practice but doesn't directly address the transition from a predictive project to an agile project. Option D emphasizes creating a scope baseline (a common practice in predictive projects) while recognizing the importance of backlog activities (an agile concept). This approach is more suitable when transitioning from a predictive to an agile project, as it maintains some level of initial scope definition while embracing agile flexibility.
upvoted 3 times
...
Abdelmonm
10 months, 2 weeks ago
Selected Answer: A
In an agile project, it's common to estimate the work the team can complete within a given time frame (e.g., a sprint) and use story sizes to understand the effort involved in each user story. This approach helps in managing and controlling the scope by prioritizing work based on business value and team capacity. The remaining work can be placed in the backlog, and adjustments can be made in subsequent iterations based on feedback and changing priorities. This iterative and adaptive approach aligns with agile principles and allows for flexibility in responding to changes.
upvoted 1 times
...
Abdelmonm
10 months, 3 weeks ago
Selected Answer: D
In agile projects, it's common to create a scope baseline that includes the high-priority and well-defined features or user stories that are essential for the initial release. The remaining features or requirements are then added to the product backlog as backlog items. This allows for flexibility and adaptability during the project, as the backlog can be reprioritized and adjusted based on changing requirements, stakeholder feedback, and evolving project needs. Agile projects often embrace the concept of a dynamic backlog, enabling teams to continuously deliver value while responding to changes and uncertainties in a more iterative and incremental manner.
upvoted 2 times
Abdelmonm
10 months, 2 weeks ago
In an agile project, it's common to estimate the work the team can complete within a given time frame (e.g., a sprint) and use story sizes to understand the effort involved in each user story. This approach helps in managing and controlling the scope by prioritizing work based on business value and team capacity. The remaining work can be placed in the backlog, and adjustments can be made in subsequent iterations based on feedback and changing priorities. This iterative and adaptive approach aligns with agile principles and allows for flexibility in responding to changes.
upvoted 1 times
...
...
Jaya12
11 months, 3 weeks ago
Selected Answer: A
Estimating the work the team can complete and defining story sizes to keep the project under control , option A is the most appropriate approach to manage and control scope in the transition to the new agile project.
upvoted 2 times
deviszont
11 months, 2 weeks ago
I have a feeling answer A is not the right one, as the Project Manager should not estimate the work or the story sizes by his/her own. She/he needs to discuss them together with the team.
upvoted 3 times
...
...
certificate988
11 months, 4 weeks ago
Selected Answer: A
Between A and D, A is most suitable answer for agile project. All scope items will be in product log and estimate for user stories can manage and control the scope. I do not understand how you can have scope baseline and backlog activities separately in agile project.
upvoted 3 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...