A project team has identified a risk and wants to accept it as an opportunity to finish a project earlier than planned. The project manager realizes that the sponsor may not accept the risk since the sponsor is risk averse.
What should the project manager do?
UppersquareCapital
Highly Voted 10 months, 1 week agovictory108
Most Recent 1 month agoKim222
2 months, 3 weeks agodatntcn3
4 months, 2 weeks agosidje
6 months agoUppersquareCapital
8 months, 3 weeks agoYUCHAN2022
9 months, 2 weeks agoTrytrio
9 months, 3 weeks agoSAJSAJ
8 months, 4 weeks agoAbdelmonm
10 months, 3 weeks agoAbdelmonm
9 months, 4 weeks agoJaya12
11 months, 3 weeks agocb4a6c4
11 months, 3 weeks agocertificate988
12 months ago