A project team has identified a risk and wants to accept it as an opportunity to finish a project earlier than planned. The project manager realizes that the sponsor may not accept the risk since the sponsor is risk averse.
What should the project manager do?
UppersquareCapital
Highly Voted 8 months, 1 week agoKim222
Most Recent 3 weeks, 2 days agodatntcn3
2 months, 2 weeks agosidje
4 months agoUppersquareCapital
6 months, 3 weeks agoYUCHAN2022
7 months, 2 weeks agoTrytrio
7 months, 3 weeks agoSAJSAJ
6 months, 3 weeks agoAbdelmonm
8 months, 3 weeks agoAbdelmonm
7 months, 3 weeks agoJaya12
9 months, 2 weeks agocb4a6c4
9 months, 3 weeks agocertificate988
9 months, 3 weeks ago