Welcome to ExamTopics
ExamTopics Logo
- Expert Verified, Online, Free.
exam questions

Exam PMP All Questions

View all questions & answers for the PMP exam

Exam PMP topic 1 question 1050 discussion

Actual exam question from PMI's PMP
Question #: 1050
Topic #: 1
[All PMP Questions]

During a project gate review meeting, it is identified that one of the project deliverables will require corrective actions to meet the project quality requirements. What should the project manager do first?

  • A. Submit a change request to update the project quality requirements for the involved project deliverable.
  • B. Update the issue log. identify the involved stakeholders, and assign resources to the corrective actions.
  • C. Update the risk register and implement the approved risk response plan for quality deviations.
  • D. Identify the resources that were responsible for the deliverable and request a team development plan.
Show Suggested Answer Hide Answer
Suggested Answer: B 🗳️

Comments

Chosen Answer:
This is a voting comment (?) , you can switch to a simple comment.
Switch to a voting comment New
Kim222
3 weeks, 2 days ago
Selected Answer: B
A clear issue has arisen, so it will be recorded in the issue log
upvoted 1 times
...
certificate988
9 months, 3 weeks ago
Selected Answer: B
B seems most suitable answer. Since issue has happened, so issue log should be updated and corrective action should be taken. But identify involved stakeholders is not required if it is software project and deployment to production is not done as per Project Gate review stage. But i think for other projects , it may be applicable.
upvoted 2 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...