A project presently in the testing stage is nearing the closing phase, which will transition the completed project to the company's operations support team. However, many new members have just been added to the operations support team who are not familiar with the project and the project's acceptance is now at risk.
What should the project manager do to mitigate this transition risk?
victory108
1 month, 1 week ago517f9da
6 months, 2 weeks agoTrytrio
9 months, 3 weeks agochlaithem
10 months, 2 weeks agocb4a6c4
11 months, 3 weeks agocertificate988
12 months ago