A project using a hybrid approach to migrate from a current system to a new and enhanced system is underway. The plan is to migrate the system in stages. However, the operations team is complaining that they are not ready to start supporting the new system.

How should the project manager effectively approach this situation?

  • A. Include knowledge transfer sessions between the project and operations teams at every stage.
  • B. Prepare detailed documentation to be shared with the operations team during project closure.
  • C. Change the project management plan to add a final stage for product handoff to the operations team.
  • D. Create a lessons learned register to include operations team training for future projects.
Show Suggested Answer Hide Answer
Suggested Answer: A 🗳️

Comments

Chosen Answer:
This is a voting comment (?) , you can switch to a simple comment.
Switch to a voting comment New
victory108
3 weeks, 3 days ago
Selected Answer: A
A. Include knowledge transfer sessions between the project and operations teams at every stage
upvoted 1 times
...
certificate988
11 months, 4 weeks ago
Selected Answer: A
C cannot be answer as it require Change control process. So, A is best option to solve this issue in current project.
upvoted 3 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...