The project manager received a claim from the client because the outcome delivered is not working properly. The project manager investigated the cause and realized that this deliverable was outsourced to an external provider, and was not made aware.
What primary tool would have helped the project manager identify this situation?
victory108
1 week, 3 days agoKim222
2 months, 4 weeks agoompk
5 months, 3 weeks ago517f9da
6 months, 1 week agoKennyMuffins
8 months, 3 weeks agohoomz
9 months agoAbdelmonm
10 months, 2 weeks agoAntoFE
10 months, 3 weeks agoAntoFE
10 months, 3 weeks agoAntoFE
10 months, 3 weeks agoSamtx99
10 months, 4 weeks agocb4a6c4
11 months agoJaya12
11 months, 4 weeks ago