The project manager received a claim from the client because the outcome delivered is not working properly. The project manager investigated the cause and realized that this deliverable was outsourced to an external provider, and was not made aware.
What primary tool would have helped the project manager identify this situation?
Kim222
4 weeks agoompk
3 months, 3 weeks ago517f9da
4 months, 1 week agoKennyMuffins
6 months, 3 weeks agohoomz
7 months agoAbdelmonm
8 months, 2 weeks agoAntoFE
8 months, 3 weeks agoAntoFE
8 months, 3 weeks agoAntoFE
8 months, 3 weeks agoSamtx99
8 months, 4 weeks agocb4a6c4
9 months agoJaya12
9 months, 4 weeks ago