Five project team members are working on a software development project. As the time line for the project is very tight, the members are working overtime to keep the project on schedule. Recently, two members submitted resignations.
What should the project manager do?
Schwery
1 month, 1 week agoKim222
1 month, 2 weeks agoompk
4 months ago517f9da
4 months, 1 week agojosephsafiran
6 months, 3 weeks agoTrytrio
7 months, 3 weeks agoAbdelmonm
8 months, 2 weeks agoodylec
9 months agojanojano
9 months ago6thEditionAndy
9 months, 2 weeks agocb4a6c4
9 months, 3 weeks agoamali999
9 months, 3 weeks agocertificate988
9 months, 3 weeks agoJaya12
9 months, 4 weeks agoJaya12
9 months, 1 week ago