Five project team members are working on a software development project. As the time line for the project is very tight, the members are working overtime to keep the project on schedule. Recently, two members submitted resignations.
What should the project manager do?
victory108
1 week, 2 days agoSchwery
3 months, 1 week agoKim222
3 months, 1 week agoompk
6 months ago517f9da
6 months, 1 week agojosephsafiran
8 months, 3 weeks agoTrytrio
9 months, 3 weeks agoAbdelmonm
10 months, 2 weeks agoodylec
11 months agojanojano
11 months ago6thEditionAndy
11 months, 2 weeks agocb4a6c4
11 months, 3 weeks agoamali999
11 months, 3 weeks agocertificate988
11 months, 3 weeks agoJaya12
11 months, 4 weeks agoJaya12
11 months, 1 week ago