exam questions

Exam PMI-RMP All Questions

View all questions & answers for the PMI-RMP exam

Exam PMI-RMP topic 1 question 110 discussion

Actual exam question from PMI's PMI-RMP
Question #: 110
Topic #: 1
[All PMI-RMP Questions]

For the last several months, a project manager for a global technology program is focused on improving the project outsourcing process and analyzing the vendor supply chain as key pieces of the cost containment strategy. Early in the project, these two areas were identified as key risks to the final delivery of the project.
Since that initial risk identification, the risk manager works to identify additional risks, as well as analyze the potential impact to the project cost baseline. After performing a cost-risk sensitivity analysis, the risk manager produces this chart.

Based on this analysis, which two risk areas should the project manager focus on to control project cost?

  • A. Vendor supply chain disruption and final system test
  • B. Vendor supply chain disruption and software design changes
  • C. Outsourcing negotiations and vendor supply chain disruption
  • D. Labor rate increases and management reviews
Show Suggested Answer Hide Answer
Suggested Answer: A 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
Azharmak
3 weeks, 4 days ago
A please simple
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...
exam
Someone Bought Contributor Access for:
SY0-701
London, 1 minute ago