Welcome to ExamTopics
ExamTopics Logo
- Expert Verified, Online, Free.
exam questions

Exam PMP All Questions

View all questions & answers for the PMP exam

Exam PMP topic 1 question 1132 discussion

Actual exam question from PMI's PMP
Question #: 1132
Topic #: 1
[All PMP Questions]

Halfway through project execution, stakeholders ask for equipment that was expected to be procured. The project manager explains that the equipment was purchased, but differs from what the stakeholders are currently asking for. This is because the initial requirements were changed during a previous meeting.

What should the project manager have done to avoid this situation?

  • A. Ensured project requirements were validated and communicated with the procurement team
  • B. Ensured changing stakeholder needs and requests were properly monitored
  • C. Ensured procurement contracts were able be canceled when situations like this arise
  • D. Ensured that communications were sent to all stakeholders when requirements change
Show Suggested Answer Hide Answer
Suggested Answer: D 🗳️

Comments

Chosen Answer:
This is a voting comment (?) , you can switch to a simple comment.
Switch to a voting comment New
victory108
3 weeks, 1 day ago
Selected Answer: D
D. Ensured that communications were sent to all stakeholders when requirements change
upvoted 1 times
...
amali999
11 months, 1 week ago
Selected Answer: D
its about communication management plan
upvoted 1 times
...
Jaya12
11 months, 2 weeks ago
Selected Answer: D
Proactively communicating changes in requirements to all stakeholders, including the procurement team, is critical in ensuring alignment between evolving project needs and procurement activities. This proactive communication aids in preventing discrepancies between purchased items and updated project specifications.
upvoted 1 times
...
certificate988
11 months, 4 weeks ago
Selected Answer: D
D is the answer as it shows better execution of communication management plan. B is part of monitor and control phase which is reactive if plan/execution is not proper.
upvoted 3 times
...
cb4a6c4
12 months ago
Selected Answer: B
Had it been monitored communication would have happened.
upvoted 2 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...