Exam PMP topic 1 question 1125 discussion

Actual exam question from PMI's PMP
Question #: 1125
Topic #: 1
[All PMP Questions]

In a highly politicized organizational environment, the stakeholders are driven by their own operational or business goals, which results in conflicting interests regarding the project. What should the project manager do to steer the stakeholders toward the collective project goal?

  • A. Anticipate, alert, and follow the risk management process.
  • B. Discuss, educate, and follow the communications management process
  • C. Detect, track, and follow the issue management process
  • D. Promote, inspire, and follow the stakeholder engagement process
Show Suggested Answer Hide Answer
Suggested Answer: D 🗳️

Comments

Chosen Answer:
This is a voting comment (?) , you can switch to a simple comment.
Switch to a voting comment New
victory108
3 weeks, 3 days ago
Selected Answer: D
D. Promote, inspire, and follow the stakeholder engagement process
upvoted 1 times
...
sidje
6 months ago
Selected Answer: D
Promouvoir : Le chef de projet doit activement promouvoir l'importance du projet et les bénéfices qu'il apportera à l'organisation dans son ensemble. Cela aide à créer une vision partagée et à motiver les parties prenantes à s'aligner sur les objectifs communs. Inspirer : Il est essentiel d'inspirer les parties prenantes en leur montrant comment leur contribution individuelle et collective mènera au succès du projet. En inspirant, le chef de projet peut surmonter les résistances et les intérêts divergents. Suivre le processus d’engagement des parties prenantes : Cela inclut la gestion continue des attentes, la communication régulière et l'implication active des parties prenantes tout au long du projet. En suivant ce processus, le chef de projet peut assurer que les parties prenantes restent engagées et alignées avec l'objectif du projet.
upvoted 2 times
...
mmhawish
9 months, 3 weeks ago
Selected Answer: B
option B is the most appropriate action in this situation to address conflicting interests among stakeholders and steer them toward the collective project goal.
upvoted 1 times
...
Delab202
10 months, 2 weeks ago
Selected Answer: D
In a highly politicized environment with conflicting stakeholder interests, the most effective approach for the project manager is: D. Promote, inspire, and follow the stakeholder engagement process. Here's why: Option A: While risk management is important, it's primarily reactive and doesn't actively address the underlying conflicting interests. Option B: Communication management helps disseminate information, but it might not be enough to shift mindsets and align competing goals. Option C: Issue management focuses on resolving specific problems, which might not necessarily bridge the gap between divergent stakeholder objectives.
upvoted 2 times
...
kevzzz
10 months, 3 weeks ago
Selected Answer: D
Promote, inspire, and follow the stakeholder engagement process--- Lead by example, promote cheer on the project.
upvoted 2 times
...
psvexam
11 months ago
Ans B I would go with an effective communication management plan to keep it clean and clear, in a politicized environment
upvoted 3 times
...
6thEditionAndy
11 months, 2 weeks ago
Selected Answer: D
The issue of pursuining your own goals is that you will not collaborate with others, or not to the extend that you should. If we inspire by example on how we engage with others, we can set an example.
upvoted 4 times
...
cb4a6c4
12 months ago
B is the correct answer!!
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...