Welcome to ExamTopics
ExamTopics Logo
- Expert Verified, Online, Free.
exam questions

Exam PMP All Questions

View all questions & answers for the PMP exam

Exam PMP topic 1 question 1077 discussion

Actual exam question from PMI's PMP
Question #: 1077
Topic #: 1
[All PMP Questions]

Organizational downsizing has resulted in the key subject matter expert (SME) resource leaving a multiyear project. What should the project manager do?

  • A. Update the stakeholder register.
  • B. Consult the project sponsor.
  • C. Refer to the resource management plan.
  • D. Modify the statement of work (SOW).
Show Suggested Answer Hide Answer
Suggested Answer: B 🗳️

Comments

Chosen Answer:
This is a voting comment (?) , you can switch to a simple comment.
Switch to a voting comment New
Kim222
3 weeks, 2 days ago
Selected Answer: B
Under normal circumstances, I think it's C. However, if you look closely at the problem, it clearly states that it is “due to downsizing of the organization.” The PM does not have authority over the organization's capabilities. You need to run to your sponsor and discuss.
upvoted 1 times
...
c8ee0e6
2 months, 1 week ago
Selected Answer: C
When a key resource like the SME leaves the project, the project manager should: 1. Refer to the resource management plan to understand the procedures for replacing or reassigning resources. 2. Identify potential risks and impacts on the project schedule, budget, and quality. 3. Develop a plan to address the gap, such as: - Reassigning tasks to other team members. - Hiring a new SME or contractor. - Training existing team members to take over the responsibilities. The resource management plan should outline the procedures for handling resource changes, ensuring minimal disruption to the project.
upvoted 1 times
...
Pmpjune152024
3 months, 2 weeks ago
Selected Answer: B
In this situation, the project manager should consult the project sponsor (option B). The project sponsor is typically responsible for providing support, resources, and guidance to the project manager, making them an essential point of contact in addressing the loss of a key SME resource.
upvoted 1 times
...
[Removed]
6 months, 3 weeks ago
Selected Answer: B
In a situation of a organizational downsize, you don't getting new rescources in replacement for the SME. So the rescource management plan will not help you. You need to check with the sponsor.
upvoted 1 times
...
hoomz
7 months ago
Selected Answer: A
Stakeholder register is the input of Resource management plan.
upvoted 1 times
...
Delab202
8 months, 1 week ago
Selected Answer: C
In the scenario where organizational downsizing results in the loss of a key Subject Matter Expert (SME) for a multiyear project, the project manager should: C. Refer to the resource management plan. The resource management plan is a part of the project management plan that provides guidance on how project resources should be categorized, allocated, managed, and released. It likely contains procedures and policies for dealing with situations like the loss of a key resource. This plan should outline steps for identifying and acquiring new resources, reallocating existing resources, and adjusting timelines and strategies to compensate for the change.
upvoted 2 times
...
Abdelmonm
8 months, 2 weeks ago
Selected Answer: C
The resource management plan outlines how resources will be identified, acquired, managed, and released. In the case of losing a key SME due to downsizing, consulting the resource management plan would provide guidance on how to address such resource-related issues.
upvoted 1 times
...
Ella008
9 months, 2 weeks ago
B: This is an organizational issue. PM needs the guidance of the Sponsor.
upvoted 1 times
...
Jaya12
9 months, 2 weeks ago
Selected Answer: C
Referring to the resource management plan can help the project manager in assessing the impact of the SME's departure, identifying the criticality of the resource, and understanding procedures for resource replacement or reallocation.
upvoted 2 times
...
Hanbyul
9 months, 3 weeks ago
Selected Answer: C
C. Refer to the resource management plan.
upvoted 2 times
...
cb4a6c4
9 months, 4 weeks ago
Selected Answer: C
Resource Management Plan will have details of hiring, reliving of resources etc, and he should refer to it.
upvoted 4 times
princeviper
9 months, 4 weeks ago
Agree with that
upvoted 1 times
...
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...