Welcome to ExamTopics
ExamTopics Logo
- Expert Verified, Online, Free.
exam questions

Exam PMP All Questions

View all questions & answers for the PMP exam

Exam PMP topic 1 question 1030 discussion

Actual exam question from PMI's PMP
Question #: 1030
Topic #: 1
[All PMP Questions]

During the execution phase of a project, one of the customer's stakeholders keeps requesting changes to the scope every week. Which three actions should the project manager take to resolve this issue? (Choose three.)

  • A. Update the relevant project documents with this obstacle.
  • B. Highlight the impacts of the changes during the next project meeting.
  • C. Adjust the project management plan to include the changes in scope.
  • D. Continue the execution as planned and defer the changes to a future phase.
  • E. Schedule a meeting with the customer to align the approach.
Show Suggested Answer Hide Answer
Suggested Answer: ABC 🗳️

Comments

Chosen Answer:
This is a voting comment (?) , you can switch to a simple comment.
Switch to a voting comment New
ced45c8
Highly Voted 8 months, 2 weeks ago
Selected Answer: ABE
how do you include change in scope without assessing its impact? C is not answer relevant project documents can be risk register, or communication management plan, stakeholder engagement,..as one of stakeholders keep requesting change, we need to assess his needs and potential impact
upvoted 5 times
...
Kim222
Most Recent 2 weeks, 5 days ago
Selected Answer: ABE
ABE IS ALRIGHT
upvoted 1 times
...
Kim222
3 weeks, 1 day ago
Selected Answer: ABE
It is ABE
upvoted 1 times
...
UppersquareCapital
4 months ago
Selected Answer: ABE
Option C is wrong - Adjusting the project management plan without a formal evaluation and approval process for each change request can lead to scope creep and project failure. Any scope changes should go through a formal change control process.
upvoted 1 times
...
drimz
6 months, 4 weeks ago
the right options are BCE
upvoted 1 times
...
Trytrio
7 months, 3 weeks ago
Selected Answer: BCE
Its for sure BCE. A. Updating the relevant project documents is also important but may not directly resolve the issue. D. Deferring the changes to a future phase should be considered based on the nature and impact of the changes, but it may not be a primary action to resolve the issue.
upvoted 2 times
...
Delab202
8 months ago
Selected Answer: ABE
Here's why the other options are not optimal choices: C. Adjust the project management plan to include the changes in scope: While incorporating some changes might be necessary after discussion, constantly rewriting the plan due to weekly requests is unsustainable and inefficient. D. Continue the execution as planned and defer the changes to a future phase: Deferring changes entirely might not be feasible if they significantly impact core functionalities or deliverables.
upvoted 1 times
...
ZBoy
8 months, 1 week ago
Selected Answer: BCE
understood why A is better than E
upvoted 1 times
...
chlaithem
8 months, 2 weeks ago
Selected Answer: BCE
B. Highlight the impacts of the changes during the next project meeting. This effectively raises awareness among all stakeholders about the consequences of these ongoing changes, including potential impact on budget, timeline, and overall project goals. C. Adjust the project management plan to include the changes in scope. This demonstrates flexibility and adaptation while ensuring proper documentation and tracking of the revised scope. Updating the plan ensures everyone involved is aligned with the new direction. E. Schedule a meeting with the customer to align the approach. This proactive communication fosters collaboration and clarifies expectations. Discuss the feasibility of the requested changes, potential trade-offs, and alternative solutions that might better meet the customer's needs while minimizing disruptions to the project plan.
upvoted 1 times
...
Abdelmonm
8 months, 3 weeks ago
Selected Answer: BCE
B. Highlighting the impacts of the changes during the next project meeting allows the project manager to communicate the consequences and implications of frequent scope changes to the project team and stakeholders. It ensures that everyone is aware of the effects on the project. C. Adjusting the project management plan to include the changes in scope is necessary to document and formalize the approved changes. This helps in maintaining clarity, transparency, and alignment with the revised project scope. E. Scheduling a meeting with the customer to align the approach is crucial for discussing the challenges arising from frequent scope changes. It provides an opportunity to understand the customer's perspective, negotiate changes, and ensure that both parties are on the same page regarding project expectations.
upvoted 2 times
...
psvexam
8 months, 4 weeks ago
Ans ABE A, B and E seems more logical
upvoted 1 times
...
FredDurst
9 months ago
Selected Answer: ABE
A. Update the relevant project documents with this obstacle. This will ensure that the issue is officially recorded and can be referred to in future discussions or decision-making processes.Highlight the impacts of the changes during the next project meeting (Option B): Openly discussing the impact of ongoing scope changes in the next project meeting serves several purposes.(Option E.) Schedule a meeting with the customer to align the approach. This will provide an opportunity to discuss the issue directly with the customer, understand their needs and expectations, and agree on a way forward that is acceptable to all parties. C might be unnecessary and disruptive if changes are frequent and minor. Also constantly adjusting the project management plan to accommodate scope changes can lead to project instability and inefficiency.
upvoted 3 times
...
6thEditionAndy
9 months, 2 weeks ago
Selected Answer: ABE
The project management plan has no information on the scope, hence no need to update that when change requests are raised.
upvoted 4 times
...
Jaya12
9 months, 2 weeks ago
Selected Answer: BCE
These actions aim to address the continuous scope changes effectively by documenting, communicating, and aligning stakeholders' expectations while incorporating approved changes into the project plan.
upvoted 2 times
...
Hanbyul
9 months, 3 weeks ago
Selected Answer: BCE
B. Highlight the impacts of the changes during the next project meeting. C. Adjust the project management plan to include the changes in scope. E. Schedule a meeting with the customer to align the approach.
upvoted 2 times
...
cb4a6c4
9 months, 4 weeks ago
Selected Answer: BCE
Answer A - Updating the document will not be of help as there is chances that the request for change in scope may continue. Instead discuss with the customer to align the request.
upvoted 2 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...