An organization is using a hybrid delivery approach for a complex project. In the iteration review, a senior manager is asking for a complete redesign of the functionality presented. This may require a significant change in the technical architecture and an additional release.
What should the project lead do first?
victory108
1 month, 1 week agoKim222
2 months, 3 weeks ago9RedFox_JB
2 months, 4 weeks agosidje
5 months, 4 weeks ago517f9da
6 months, 2 weeks agokevzzz
8 months, 1 week agohoomz
9 months, 1 week agoTrytrio
9 months, 3 weeks agoUppersquareCapital
10 months, 1 week agochlaithem
10 months, 2 weeks agoAbdelmonm
10 months, 3 weeks agoSamtx99
11 months, 1 week agoUppersquareCapital
10 months, 1 week agoWaynelau
11 months, 1 week agoJaya12
11 months, 3 weeks agocb4a6c4
12 months ago