A project manager is leading a team that is new to agile. During the kickoff meeting, one team member asks how risks will be managed using agile approaches.
How should the project manager respond?
A.
Risk management is a collaborative effort and will be managed during each iteration.
B.
Risks are managed by the project manager and forecasted at the beginning of each project.
C.
Risks will be managed during a retrospective session with all of the team members.
D.
Risks are managed by the team and they will be analyzed during risk management kickoff.
A. Risk management is a collaborative effort and will be managed during each iteration.
Explanation: In agile approaches, risk management is a continuous and collaborative effort involving the entire team. Risks are identified, assessed, and addressed during each iteration, allowing the team to respond to them promptly and effectively.
A voting comment increases the vote count for the chosen answer by one.
Upvoting a comment with a selected answer will also increase the vote count towards that answer by one.
So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.
victory108
5 days, 18 hours ago517f9da
6 months, 1 week agommhawish
9 months, 3 weeks agocb4a6c4
12 months ago