A project in the execution phase is part of a large transformation program. The project manager for this project reports to a program manager and also heads the steering committee for this project. A steering committee meeting will be held in the following 2 weeks, during which the approach to measure the schedule performance of the project thus far will be presented.
What should the project manager do in preparation for this meeting?
victory108
1 week, 2 days agoKim222
3 months, 1 week agoUppersquareCapital
10 months, 2 weeks agoAbdelmonm
10 months, 2 weeks agoodylec
11 months ago