A key project team member had an accident and will be in the hospital for at least two months. The backlog items the team member was working on have been delayed since the team member was the only person who knew how to complete them.
What could the project manager have done to avoid this situation?
Kim222
2 weeks, 5 days agoompk
4 months agonqbaotd
3 months ago517f9da
4 months, 1 week ago[Removed]
6 months, 3 weeks agoTrytrio
7 months, 3 weeks agodinhnghia
7 months, 3 weeks agoAbdelmonm
8 months, 2 weeks agochlaithem
8 months, 2 weeks agoodylec
8 months, 3 weeks agoElla008
9 months, 2 weeks ago6thEditionAndy
9 months, 2 weeks agoJaya12
9 months, 3 weeks agoHanbyul
9 months, 3 weeks agocb4a6c4
9 months, 4 weeks agoprinceviper
10 months ago