Welcome to ExamTopics
ExamTopics Logo
- Expert Verified, Online, Free.
exam questions

Exam PMP All Questions

View all questions & answers for the PMP exam

Exam PMP topic 1 question 924 discussion

Actual exam question from PMI's PMP
Question #: 924
Topic #: 1
[All PMP Questions]

A project manager is initiating a project to create a new service that has never been done before in their organization. The project manager is trying to determine what resources are required for their project team but is receiving conflicting resource requirements from the team, sponsor, and key stakeholders.

What should the project manager do next?

  • A. Identify the resources that are agreed upon to initiate the project and request additional resources later.
  • B. Determine if there is a subject matter expert (SME) who has expertise in the new service to assist with resource requirements.
  • C. Evaluate and prioritize the resource requests from the project's key stakeholders.
  • D. Evaluate the resource options and propose alternatives to the project team for their approval.
Show Suggested Answer Hide Answer
Suggested Answer: B 🗳️

Comments

Chosen Answer:
This is a voting comment (?) , you can switch to a simple comment.
Switch to a voting comment New
victory108
5 days, 18 hours ago
Selected Answer: B
B. Determine if there is a subject matter expert (SME) who has expertise in the new service to assist with resource requirements
upvoted 1 times
...
UppersquareCapital
6 months ago
Selected Answer: B
Since the project involves creating a new service that has never been done before in the organization, identifying an SME with relevant experience is crucial. An SME can provide valuable insights and guidance on the specific resources needed based on their expertise and experience with similar projects. An SME can help clarify and validate the conflicting resource requirements from the team, sponsor, and stakeholders. Their expert opinion can serve as a neutral and informed basis for determining the necessary resources, reducing ambiguity and conflict.
upvoted 2 times
...
517f9da
6 months, 1 week ago
Selected Answer: B
No need to overthink on this. B. Determine if there is a subject matter expert (SME) who has expertise in the new service to assist with resource requirements. Explanation: Consulting a subject matter expert (SME) with expertise in the new service can provide valuable insights and help clarify the necessary resources, ensuring that the project manager receives accurate and informed resource requirements.
upvoted 1 times
...
[Removed]
8 months, 3 weeks ago
Selected Answer: B
Best to work with a expert
upvoted 1 times
...
Trytrio
9 months, 3 weeks ago
Selected Answer: C
C - since its a broader approach then B
upvoted 1 times
...
josephsafiran
10 months ago
Selected Answer: B
In this situation, the project manager should: **B. Determine if there is a subject matter expert (SME) who has expertise in the new service to assist with resource requirements.** Given that the service is new to the organization, an SME with expertise in the area can provide valuable insights into what resources are necessary. This can help resolve the conflicting resource requirements from the team, sponsor, and key stakeholders. The SME's expertise can guide the project manager in making informed decisions about resource allocation, which is crucial for the successful initiation of the project. Therefore, Option B is the most appropriate action.
upvoted 4 times
...
xcjxcj
10 months, 1 week ago
Selected Answer: A
A. Identify the resources that are agreed upon to initiate the project and request additional resources later
upvoted 1 times
...
UppersquareCapital
10 months, 2 weeks ago
Selected Answer: D
This involves bringing together all stakeholders to discuss the differing perspectives, understand the reasons behind the conflicting requirements, and work towards a consensus on the most appropriate resources for the project. Options A and B are more focused on immediate actions, but they may not address the underlying conflicts and may lead to further issues later in the project. Option C suggests evaluating and prioritizing resource requests from key stakeholders, which is a step in the right direction. However, it is important to involve the entire project team in the evaluation and decision-making process.
upvoted 2 times
UppersquareCapital
6 months ago
Sorry, correct answer is option B
upvoted 1 times
...
...
Abdelmonm
10 months, 2 weeks ago
Selected Answer: D
When faced with conflicting resource requirements, it's essential for the project manager to evaluate the available options and propose alternatives to the project team. This involves a collaborative approach to reach a consensus and agreement on the necessary resources. By involving the project team in the decision-making process, the project manager can address conflicting perspectives and ensure that the resource requirements are well-understood and supported.
upvoted 2 times
UppersquareCapital
6 months ago
Proposing alternatives without the necessary expertise might lead to suboptimal resource allocation. Involving an SME ensures that the proposed alternatives are based on informed knowledge and experience. Therefore, option B is the best course of action as it leverages expert knowledge to accurately determine the resource requirements for a project involving a new and unfamiliar service.
upvoted 2 times
...
...
mesacgon
10 months, 3 weeks ago
Voy por D porque considera a todo el equipo y el PM no debe priorizar las solicitudes de requerimiento del todo.
upvoted 1 times
...
odylec
10 months, 4 weeks ago
Selected Answer: C
C is the answer
upvoted 2 times
...
cb4a6c4
11 months, 3 weeks ago
Selected Answer: B
Its B. New service that has never been done - Better to have an expert advise.
upvoted 2 times
...
Jaya12
11 months, 3 weeks ago
Selected Answer: C
evaluating and prioritizing resource requests from the project's key stakeholders will enable the project manager to gain a clearer understanding of essential resources needed for project initiation and foster alignment among stakeholders towards a more unified resource plan.
upvoted 2 times
...
cb4a6c4
12 months ago
Selected Answer: D
Never been done before in the organization - I go with D
upvoted 2 times
...
princeviper
12 months ago
Selected Answer: B
Since the project is new to them, I guess SME is required.
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...