A company has always acquired very specialized services from local companies for its projects. During the planning stage for a regulatory project, the project manager is informed that local vendors would not be able to operate due to an unexpected major event. There is an option to hire the same services from companies in other countries.
What should the project manager do in this situation?
victory108
1 month, 1 week ago9RedFox_JB
2 months, 4 weeks agoSchwery
3 months, 2 weeks agoompk
6 months, 2 weeks agokevzzz
8 months, 1 week agorshankhwa
8 months, 2 weeks agohoomz
9 months, 1 week agoUppersquareCapital
10 months, 1 week agochlaithem
10 months, 2 weeks agoAbdelmonm
10 months, 3 weeks agocb4a6c4
12 months agoHesTa1234
1 year ago6thEditionAndy
11 months, 2 weeks agocc02995
11 months, 2 weeks agoUppersquareCapital
10 months, 1 week ago