A company has always acquired very specialized services from local companies for its projects. During the planning stage for a regulatory project, the project manager is informed that local vendors would not be able to operate due to an unexpected major event. There is an option to hire the same services from companies in other countries.
What should the project manager do in this situation?
victory108
3 weeks, 4 days ago9RedFox_JB
2 months, 2 weeks agoSchwery
3 months agoompk
6 months, 1 week agokevzzz
7 months, 3 weeks agorshankhwa
8 months agohoomz
8 months, 3 weeks agoUppersquareCapital
10 months agochlaithem
10 months agoAbdelmonm
10 months, 1 week agocb4a6c4
11 months, 2 weeks agoHesTa1234
11 months, 3 weeks ago6thEditionAndy
11 months agocc02995
11 months agoUppersquareCapital
10 months ago