Welcome to ExamTopics
ExamTopics Logo
- Expert Verified, Online, Free.
exam questions

Exam PMP All Questions

View all questions & answers for the PMP exam

Exam PMP topic 1 question 894 discussion

Actual exam question from PMI's PMP
Question #: 894
Topic #: 1
[All PMP Questions]

A team has noticed a labeling mistake in two different prototypes. The mistake resulted in a need to apply a different destructive testing plan for each prototype. This resulted in a decline in team morale.

What should the project lead do?

  • A. Lead the team through the next sprint to prevent a similar issue.
  • B. Influence stakeholders to support the team allowing recovery within limits.
  • C. Bring in subject matter experts (SMEs) to coach the team.
  • D. Use cost and time contingencies to mitigate a project baseline impact.
Show Suggested Answer Hide Answer
Suggested Answer: B 🗳️

Comments

Chosen Answer:
This is a voting comment (?) , you can switch to a simple comment.
Switch to a voting comment New
victory108
1 week, 4 days ago
Selected Answer: B
B. Influence stakeholders to support the team allowing recovery within limits
upvoted 1 times
...
[Removed]
8 months, 3 weeks ago
Selected Answer: C
I think the best is the support the team with a SME to solve the issue.
upvoted 1 times
...
Trytrio
9 months, 3 weeks ago
Selected Answer: B
Upon reassessment, option B, "Influence stakeholders to support the team allowing recovery within limits," remains the most suitable choice for addressing the team morale issue resulting from the labeling mistake while keeping the project on track.
upvoted 2 times
...
dinhnghia
9 months, 3 weeks ago
I believe the answer is A. The root cause is team mistaked labeling 2 different prototypes. How to ensure this problem will not occur again and how many recovery limits does the team need? What happen if team exceed the limit? So A is the answer. Team needs organizing the retrospective meeting to know the cause of this mistake and plan a preventing plan
upvoted 2 times
...
UppersquareCapital
10 months, 2 weeks ago
Selected Answer: B
In this situation, it's important for the project lead to address the issue promptly. Influencing stakeholders to support the team and allowing recovery within limits is a constructive approach. By gaining support from stakeholders, the project lead can work towards mitigating the negative impact on team morale. It also opens the door for the team to rectify the labeling mistake and adjust the testing plans, with the understanding that mistakes happen and recovery efforts are supported. This approach fosters a more positive team environment and encourages a collaborative response to challenges.
upvoted 2 times
...
odylec
11 months ago
Selected Answer: A
A is the answer
upvoted 2 times
odylec
11 months ago
It's not job of the stakeholders to support the team but of the PM. So it cannot be B.
upvoted 1 times
...
...
cb4a6c4
11 months, 2 weeks ago
Selected Answer: B
Option B - Bringing in a SME for labeling issue would not be of much help. Supporting the team will boast their morale.
upvoted 3 times
...
Mmotun
1 year ago
C should be the answer
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...