A development team member learned that one of the product features delivered in the last sprint would have greater business value if a small enhancement was made to the feature.
What should the project manager do next?
A.
Conduct another sprint planning meeting and add the necessary story.
B.
Discuss this feature in the next sprint planning meeting.
C.
Discuss this feature during the upcoming retrospective meeting.
D.
Advise the team member to better prepare before sprint planning.
The answer is clearly B. A. Sprint planning and story additions are done by the PO.
C. Sprint retrospective is a way to discuss agile methodology.
D. If you choose this, give up the test
B. Discuss this feature in the next sprint planning meeting.
Explanation: Discussing the feature enhancement in the next sprint planning meeting ensures that the team can evaluate its priority, estimate the effort required, and decide whether to include it in the upcoming sprint. This approach maintains the structured process of planning and prioritizing work while considering the potential business value of the enhancement.
Sprint planning is the right time to discuss and prioritize new work items for the upcoming sprint, including enhancements to existing features. This allows the team to assess the impact of the enhancement on their current workload and plan accordingly. Remember, agile methodologies encourage continuous improvement and adaptation, so it’s important to be open to changes that can deliver greater value.
C is the answer.
In Agile, the project manager should discuss a small enhancement to a delivered product feature during the upcoming retrospective meeting (Option C). Retrospectives provide a dedicated space for team reflection, fostering a collaborative environment for continuous improvement. This approach leverages the iterative nature of Agile methodologies and ensures the entire team's involvement in decision-making.
B should be the answer as it is not necessary to inform team member to be prepared as it will be on Agenda of planning, so it is expected for team member to share the details in the meeting.
D: Advise the team member to better prepare before sprint planning.
upvoted 1 times
...
Log in to ExamTopics
Sign in:
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.
Upvoting a comment with a selected answer will also increase the vote count towards that answer by one.
So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.
victory108
4 days, 13 hours agoKim222
3 months, 1 week agoLNX_RM_Admin
6 months, 1 week ago517f9da
6 months, 1 week agoVictory007
10 months, 1 week agoodylec
10 months, 3 weeks agoNmamma
11 months, 2 weeks agocertificate988
11 months, 3 weeks agocb4a6c4
12 months agoSamT
1 year ago