Welcome to ExamTopics
ExamTopics Logo
- Expert Verified, Online, Free.
exam questions

Exam PgMP All Questions

View all questions & answers for the PgMP exam

Exam PgMP topic 1 question 374 discussion

Actual exam question from PMI's PgMP
Question #: 374
Topic #: 1
[All PgMP Questions]

During program execution, a program manager receives feedback from an executive sponsor that some program stakeholders may not understand the intended benefits of the program.
Which will provide the greatest value to clarify stakeholder perceptions?

  • A. Performing a stakeholder analysis
  • B. Updating the stakeholder communications requirements
  • C. Redistributing the benefits management plan
  • D. Redistributing the program charter
Show Suggested Answer Hide Answer
Suggested Answer: B 🗳️

Comments

Chosen Answer:
This is a voting comment (?) , you can switch to a simple comment.
Switch to a voting comment New
tungdt
2 months, 2 weeks ago
B is correct
upvoted 1 times
tungdt
2 months ago
Sorry, D is correct
upvoted 1 times
...
...
happykaur
8 months, 2 weeks ago
Selected Answer: C
To clarify stakeholder perceptions about the intended benefits of the program, the most valuable approach would be: C. Redistributing the benefits management plan The benefits management plan provides detailed information about the intended benefits of the program, how they align with business objectives, and how they will be measured and realized. Redistributing this plan to stakeholders can help clarify any misunderstandings or misconceptions about the program's intended benefits.
upvoted 1 times
...
hanyulin
8 months, 3 weeks ago
Selected Answer: D
D is the best answer. The chat purpose is what benefit must be implemented, the benefits management plan purpose is when and how to implement benefit. So the D is the best answer.
upvoted 1 times
...
[Removed]
9 months ago
Selected Answer: C
C. Redistributing the benefits management plan. Redistributing the benefits management plan will provide the greatest value to clarify stakeholder perceptions regarding the intended benefits of the program. The benefits management plan specifically outlines the intended benefits of the program, how these benefits align with the program's objectives, and the methods for achieving and measuring them. By redistributing this plan, the program manager can effectively communicate the value and purpose of the program, directly addressing any misunderstandings or lack of clarity about the program's benefits among the stakeholders. This action ensures that stakeholders have the correct information and a clear understanding of what the program aims to achieve.
upvoted 1 times
...
hanyulin
9 months, 2 weeks ago
Selected Answer: D
D should be right.
upvoted 1 times
...
ekk1983
10 months, 2 weeks ago
I go with C
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...