Exam PgMP topic 1 question 10 discussion

Actual exam question from PMI's PgMP
Question #: 10
Topic #: 1
[All PgMP Questions]

You are the program manager of the BHG Program. One of the projects in your program will be using new materials that are somewhat untested. You are worried that there may be delays and waste because the project team is unaware of how to accurately use these materials. You elect to send the people that will be using the new materials through training on how to complete their project work. You also allow them to purchase some of the materials to experiment on their use before the actual project work is to be done. You want to ensure that mistakes do not enter into the project. What type of action have you provided in this scenario?

  • A. This is an example of a preventive action.
  • B. This is an example of team development.
  • C. This is an example of quality assurance.
  • D. This is an example of a corrective action.
Show Suggested Answer Hide Answer
Suggested Answer: A 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
AmrKHALIL
1 month ago
Selected Answer: A
Preventive Action: This is a proactive measure taken to avoid potential problems or risks before they occur. In this scenario, you are taking steps (training and practice with the materials) to prevent delays and mistakes caused by the team’s unfamiliarity with the new materials.
upvoted 1 times
...
Sergey_k
5 months, 4 weeks ago
A is the right answer
upvoted 1 times
...
tungdt
5 months, 4 weeks ago
A is right anwser
upvoted 1 times
...
mfshabana
1 year, 1 month ago
A. This is an example of a preventive action. A preventive action is taken to proactively avoid potential issues or problems before they occur. In this case, you are taking steps to prevent potential delays and waste by providing training on the use of new materials and allowing the project team to experiment with the materials before the actual project work begins. This proactive approach is aimed at preventing mistakes and ensuring that the project goes smoothly.
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel