A project manager in your program has estimated the cost of a program to be $145,000. As the project manager's project comes close to completion, the project manager realizes that he has still $27,876 left in his project budget. He decides to add some additional features to the project's deliverables in an effort to use the remaining budget. These additions will add value to the project and the project customer is likely to enjoy these new features. This is an example of what term?

  • A. Gold plating
  • B. Errors and omissions
  • C. Expert judgment by the project manager
  • D. Value added change
Show Suggested Answer Hide Answer
Suggested Answer: A 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
AmrKHALIL
1 month ago
Selected Answer: A
Gold plating refers to the practice of adding extra features or deliverables to a project that were not part of the original scope or agreed-upon requirements. In this scenario, the project manager is using the remaining budget to add additional features that were not requested by the customer, even though these additions might be appreciated. This is not recommended in project management because it can lead to: Scope creep. Misaligned customer expectations. Potential risks or costs that were not accounted for
upvoted 1 times
...
tungdt
5 months, 4 weeks ago
Answer is A
upvoted 2 times
...
mfshabana
1 year, 1 month ago
A. Gold plating Gold plating refers to the practice of adding extra features or enhancements to a project deliverable that were not originally specified in the project scope. In this case, the project manager is adding additional features to the project's deliverables with the remaining budget, even though these features were not initially part of the agreed-upon scope. While the intention may be to provide additional value, it can lead to scope creep and should be carefully managed to ensure that it aligns with the project objectives and requirements.
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.