Actual exam question from PMI's PgMP
Question #: 5
Topic #: 1
[All PgMP Questions]

You are the program manager of the NHQ Program. You are working with your program team to ensure that the work in the program is done accurately and according to scope. You are also reviewing the team inspection process that will need to be done to ensure that the work is being done according to the scope. If the work is found to be defective it will need to be corrected before the program customers can inspect the work. What process are you completing to ensure that the work is done accordingly to scope?

  • A. Quality control
  • B. Scope verification
  • C. Quality assurance
  • D. Planning
Show Suggested Answer Hide Answer
Suggested Answer: A 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
AmrKHALIL
1 day, 10 hours ago
Selected Answer: A
Quality control focuses on monitoring and verifying that the work meets the defined quality standards and scope requirements. It includes inspecting deliverables to ensure they conform to requirements and identifying defects so they can be corrected before final acceptance. In this scenario, you are reviewing the inspection process and identifying defects that need to be addressed, which aligns with quality control activities.
upvoted 1 times
...
Pivste1
2 weeks, 6 days ago
Selected Answer: C
The answer is QA: Focuses on the process itself and how work is being done. Is preventive in nature, aiming to prevent defects from occurring. Involves regular audits to ensure proper procedures are being followed. Evaluates whether the program is adhering to organizational standards and policies. Is conducted throughout the program lifecycle. Typically involves reviewing program management processes, methodologies, and tools. Vs. quality control: Focuses on the deliverables and verifying specific results. Is detective in nature, identifying defects after they occur. Involves inspection and testing of program outputs. Measures specific program components against established quality standards. Is performed at specific checkpoints or milestones. Typically involves measuring, examining, and testing specific program components.
upvoted 1 times
...
tungdt
4 months, 4 weeks ago
Answer is A
upvoted 2 times
...
LuanND
6 months, 3 weeks ago
Selected Answer: A
totally agree with A
upvoted 3 times
...
Ahsan_tirmizi
6 months, 4 weeks ago
yes Quality assurance
upvoted 1 times
...
mfshabana
1 year ago
Quality assurance involves processes and activities that ensure the project is being executed and the deliverables are being produced according to the planned scope, standards, and requirements. It includes activities such as process audits, reviews, and inspections to identify and correct any defects or issues in the work before it is presented to the program customers. This helps in preventing defects and ensuring the overall quality of the project.
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...