exam questions

Exam PMP All Questions

View all questions & answers for the PMP exam

Exam PMP topic 1 question 879 discussion

Actual exam question from PMI's PMP
Question #: 879
Topic #: 1
[All PMP Questions]

A project sponsor asked the product owner to deliver the functionality that provides the highest return on investment (ROI) as soon as possible. Which artifact should the project lead use to track benefits?

  • A. Requirements backlog
  • B. Product backlog
  • C. Project charter
  • D. Project scope
Show Suggested Answer Hide Answer
Suggested Answer: B 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
Trytrio
8 months, 4 weeks ago
Selected Answer: B
To track benefits and return on investment (ROI), the project lead should use the Product Backlog (Option B). The Product Backlog contains a prioritized list of features, functionalities, and user stories, and it's a valuable tool for tracking the delivery of value and benefits throughout the project. The most valuable items with the highest ROI should be placed at the top of the Product Backlog and are typically delivered earlier in the project, allowing for the tracking of benefits as they are implemented and realized.
upvoted 2 times
...
125bb38
9 months ago
Check project scope.
upvoted 1 times
...
Abdelmonm
9 months, 1 week ago
Selected Answer: B
In Agile project management, the Product Backlog is a prioritized list of all the features, enhancements, and fixes that need to be addressed in the product. It is ordered based on the value it delivers to the customer or stakeholders. Therefore, when the project sponsor wants to focus on delivering functionality with the highest return on investment (ROI), the project lead should refer to the Product Backlog. The items at the top of the Product Backlog are the highest priority and are typically the ones that provide the most value. Tracking benefits and return on investment can be effectively managed by managing and prioritizing the Product Backlog.
upvoted 1 times
...
chlaithem
9 months, 3 weeks ago
Selected Answer: B
Product Backlog is specifically designed to manage and prioritize product increments based on their value and user needs. It can be adapted to accommodate ROI considerations by: Estimating the ROI of each backlog item: This can be done through techniques like cost-benefit analysis or net present value calculations. Prioritizing based on ROI: Backlog items with higher ROI can be moved closer to the top of the queue, ensuring the functionality with the highest ROI is delivered first. Tracking actual benefits realized: As functionalities are delivered, the project lead can track the actual benefits achieved and compare them to the estimated ROI, providing valuable insights for future iterations.
upvoted 2 times
...
odylec
10 months, 1 week ago
Selected Answer: B
B is the answer
upvoted 1 times
...
cb4a6c4
10 months, 3 weeks ago
Selected Answer: D
Why not D. Project scope offers more granular information that can be use to calculate the ROI?
upvoted 2 times
...
Jaya12
10 months, 4 weeks ago
Selected Answer: C
The project charter typically outlines the high-level vision, objectives, stakeholders, and key milestones of the project. While it might not contain detailed tracking of benefits realization or a comprehensive Benefits Management Plan, it often highlights the overarching goals and expected outcomes of the project, which could include references to benefits or ROI.
upvoted 1 times
...
loscoe
11 months, 1 week ago
Selected Answer: B
Keyword is "track". The charter outlines the expected benefits, while the backlog tracks their priority & delivery/realization.
upvoted 3 times
...
huynq185
11 months, 3 weeks ago
Selected Answer: C
While the Product Backlog helps the development team understand what needs to be worked on next, it may not be the artifact used specifically for tracking benefits. The Project Charter (Option C) is often the document that outlines the expected benefits and return on investment for the project. It serves as a higher-level document that provides context and goals for the project, including the anticipated benefits.
upvoted 2 times
...
kevzzz
1 year ago
Selected Answer: B
The backlog is a well-defined list of tasks. According to Atlassian, a product backlog is a prioritized list of work for the development team that is derived from the roadmap and its requirements. The most important items are shown at the top of the product backlog so the team knows what to deliver first.
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...
exam
Someone Bought Contributor Access for:
SY0-701
London, 1 minute ago