A project team is reviewing the project business document for a phase-gate session and discovers that the benefits need to be validated by the project sponsor.
Unfortunately, the project sponsor was recently changed, and the new sponsor does not seem to be supportive.
What should the project manager do to address this situation?
David8989
Highly Voted 1 year agofunmis4
Most Recent 1 month, 4 weeks agoKim222
3 months, 2 weeks ago0d83051
7 months agoAshPik
8 months, 1 week agoTrytrio
9 months, 3 weeks agojosephsafiran
10 months agoAbdelmonm
10 months, 1 week agoloscoe
12 months agoUncle_Lucifer
1 year agoDavid983
1 year, 1 month ago