exam questions

Exam PMP All Questions

View all questions & answers for the PMP exam

Exam PMP topic 1 question 860 discussion

Actual exam question from PMI's PMP
Question #: 860
Topic #: 1
[All PMP Questions]

A consultancy firm is finally selected and contracted for a project following an extensive and competitive procurement process. A few months into project execution, the client asks the project manager why the consultant is contracted for only 18 months instead of the full 32-month-long project. The project manager will need to carry out an unplanned second bidding process to ensure services are in place until the end of the project.

What should the project manager have done to prevent this?

  • A. Developed a detailed, phased procurement management plan including all activities required and had the client approve it.
  • B. Included the client in all negotiation phases with the consultancy to obtain their advanced approval before signing the contract.
  • C. Agreed beforehand with the client on the frequency of reporting on the status of the procurement activities within the project.
  • D. Prepared and negotiated a second contract with the consultancy firm for the remaining 14 months after the first contract signature.
Show Suggested Answer Hide Answer
Suggested Answer: A 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
David983
6 months ago
Selected Answer: A
A. Developed a detailed, phased procurement management plan including all activities required and had the client approve it.
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...
exam
Someone Bought Contributor Access for:
SY0-701
London, 1 minute ago