Question #: 837
Topic #: 1
[All PMP Questions]

A project manager is working with an agile team to enhance a product. Due to a tight deadline, the team is trying to crash the schedule by engaging multiple resources to work on the project simultaneously. However, the technical environment is configured to allow only one resource to work on a feature at a time.
The team plans to upgrade the technical environment but is unable to agree on a way forward.

What should the project manager do first?

  • A. Add this conflict to the agenda for discussion at the next daily standup meeting.
  • B. Conduct a consensus-building session to decide how to approach the next set of work.
  • C. Conduct a planning session to decide how to approach the next set of work.
  • D. Escalate the issue to the product owner for resolution.
Show Suggested Answer Hide Answer
Suggested Answer: B 🗳️

Comments

Chosen Answer:
This is a voting comment (?) , you can switch to a simple comment.
Switch to a voting comment New
Kim222
2 weeks, 6 days ago
Selected Answer: B
This is B
upvoted 1 times
...
Abdelmonm
8 months ago
Selected Answer: C
In an Agile project, when facing a constraint or impediment, it's important to address it during the planning session. The planning session provides an opportunity for the team to discuss challenges, identify potential solutions, and collaboratively decide on the best approach for the next set of work. This proactive approach aligns with Agile principles of self-organization and continuous improvement, allowing the team to find solutions collectively and move forward effectively.
upvoted 1 times
...
kevzzz
8 months, 1 week ago
Selected Answer: B
The team is unable to agree on a path forward. Brainstorming, multi-voting, and nominal group technique are structured methods for helping teams discuss issues, develop ideas and solutions, and reach a decision that everyone can live with.
upvoted 1 times
...
victory108
11 months, 2 weeks ago
Selected Answer: B
B. Conduct a consensus-building session to decide how to approach the next set of work
upvoted 1 times
...
adingmaki
11 months, 2 weeks ago
D. Given the tight nature of deadline, consensus might not be a very good option since it is time consuming. PMI library. https://www.pmi.org/learning/library/project-group-decision-making-process-6797
upvoted 1 times
adingmaki
11 months, 2 weeks ago
I MEAN C.
upvoted 1 times
...
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...