A project is being executed in multiple phases. Midway through, the customer wants to bring in a new tool to replace the existing software in the project as part of their improvement program. The project team has identified the changes and submitted the change request to the customer for approval
What should the project manager do next?
d370e49
1 week, 2 days agoKim222
1 month, 1 week agoUppersquareCapital
4 months agoLNX_RM_Admin
4 months, 1 week agojosephsafiran
7 months, 4 weeks agoAbdelmonm
8 months ago6thEditionAndy
9 months, 2 weeks agoUncle_Lucifer
10 months, 4 weeks agokevzzz
11 months agosk8chick68
10 months, 3 weeks agopsvexam
11 months, 2 weeks agoprokat_mashin_na_vicecity
11 months, 1 week agoUncle_Lucifer
10 months, 4 weeks agoSumbo
11 months, 2 weeks agoUncle_Lucifer
10 months, 4 weeks ago