A project is being executed in multiple phases. Midway through, the customer wants to bring in a new tool to replace the existing software in the project as part of their improvement program. The project team has identified the changes and submitted the change request to the customer for approval
What should the project manager do next?
d370e49
2 months, 2 weeks agoKim222
3 months, 2 weeks agoUppersquareCapital
6 months, 1 week agoLNX_RM_Admin
6 months, 2 weeks agojosephsafiran
10 months agoAbdelmonm
10 months, 1 week ago6thEditionAndy
11 months, 3 weeks agoUncle_Lucifer
1 year, 1 month agokevzzz
1 year, 1 month agosk8chick68
1 year agopsvexam
1 year, 1 month agoprokat_mashin_na_vicecity
1 year, 1 month agoUncle_Lucifer
1 year, 1 month agoSumbo
1 year, 1 month agoUncle_Lucifer
1 year, 1 month ago