A project is being executed in multiple phases. Midway through, the customer wants to bring in a new tool to replace the existing software in the project as part of their improvement program. The project team has identified the changes and submitted the change request to the customer for approval
What should the project manager do next?
STAR666
4 months, 4 weeks agod370e49
9 months, 3 weeks agoKim222
10 months, 4 weeks agoUppersquareCapital
1 year, 1 month agoLNX_RM_Admin
1 year, 1 month agojosephsafiran
1 year, 5 months agoAbdelmonm
1 year, 5 months ago6thEditionAndy
1 year, 7 months agoUncle_Lucifer
1 year, 8 months agokevzzz
1 year, 8 months agosk8chick68
1 year, 8 months agopsvexam
1 year, 8 months agoprokat_mashin_na_vicecity
1 year, 8 months agoUncle_Lucifer
1 year, 8 months agoSumbo
1 year, 8 months agoUncle_Lucifer
1 year, 8 months ago8a6d137
1 week, 5 days ago