A team member has encountered a technical issue, similar to the one faced in a successfully closed project. However, the team member did not know about the previous project and would like to resolve the issue on their own.

What should the project manager do?

  • A. Reach out to the project manager of the previous project for assistance.
  • B. Allow the team member to work through the issue as a training opportunity.
  • C. Improve the risk management strategy and risk monitoring.
  • D. Share the lessons learned from the previous project with the team member.
Show Suggested Answer Hide Answer
Suggested Answer: D 🗳️

Comments

Chosen Answer:
This is a voting comment (?) , you can switch to a simple comment.
Switch to a voting comment New
martinx84
2 months ago
Selected Answer: D
Share lessons learned, they are available
upvoted 1 times
...
Victory007
8 months, 1 week ago
Selected Answer: D
This will help the team member understand how a similar issue was resolved in the past, which can provide valuable insights and potentially save time and resources. It also promotes knowledge sharing and continuous learning within the team.
upvoted 1 times
...
victory108
11 months, 2 weeks ago
Selected Answer: D
D. Share the lessons learned from the previous project with the team member
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...