A project manager working on a large-scale network implementation is frustrated with the hardware supplier. Their deliveries have been consistently late and frequently do not have vital components. The project manager's company has decided to cancel the contract and move to a new supplier, but the only other option is an overseas company.
What should the project manager do first to proceed with this change?
Kim222
7 months, 4 weeks agoju3504
11 months, 1 week agoAbdelmonm
1 year, 2 months agojosephsafiran
1 year, 3 months agochlaithem
1 year, 3 months agoodylec
1 year, 4 months agocb4a6c4
1 year, 4 months agoChezQW
1 year, 6 months agoOnly12go
1 year, 6 months agoadingmaki
1 year, 6 months agovictory108
1 year, 6 months agoDavid983
1 year, 6 months agoDavid983
1 year, 6 months ago