A project manager working on a large-scale network implementation is frustrated with the hardware supplier. Their deliveries have been consistently late and frequently do not have vital components. The project manager's company has decided to cancel the contract and move to a new supplier, but the only other option is an overseas company.
What should the project manager do first to proceed with this change?
Kim222
2 weeks, 6 days agoju3504
4 months agoAbdelmonm
7 months, 3 weeks agojosephsafiran
7 months, 4 weeks agochlaithem
8 months, 2 weeks agoodylec
9 months agocb4a6c4
9 months, 2 weeks agoChezQW
11 months agoOnly12go
11 months agoadingmaki
11 months, 2 weeks agovictory108
11 months, 2 weeks agoDavid983
11 months, 3 weeks agoDavid983
11 months, 3 weeks ago