All activities for Project A are ahead of schedule, except for one activity that is on the critical path. The resource manager is requesting that the team members join Project B, which is an important project in the organization that is behind schedule.
What should the project manager do?
pigmeatpig
1Â week, 6Â days agoSTAR666
2Â months agoAbdelmonm
8Â months, 3Â weeks agoloscoe
10Â months, 3Â weeks ago[Removed]
11Â months ago[Removed]
11Â months agokevzzz
11Â months, 3Â weeks agoDavid983
11Â months, 3Â weeks agoDavid983
11Â months, 3Â weeks agoOnly12go
11Â months, 3Â weeks agoadingmaki
12Â months agonemm235
1Â year ago