A project manager is managing a hybrid project. A stakeholder has directly contacted a team member and has requested a change. Due to the request, the team member was distracted from their work, which caused a loss in productivity
What should the team member do?
victory108
Highly Voted 11 months, 2 weeks agoKim222
Most Recent 2 weeks, 6 days agohoomz
7 months agojosephsafiran
8 months agoBamBT
8 months, 2 weeks agomesacgon
9 months agocb4a6c4
9 months, 2 weeks agoJaya12
9 months, 2 weeks agoprinceviper
10 months agosudersonfernando
11 months, 3 weeks ago