A project manager is managing a hybrid project. A stakeholder has directly contacted a team member and has requested a change. Due to the request, the team member was distracted from their work, which caused a loss in productivity
What should the team member do?
victory108
Highly Voted 1 year, 1 month agoAmirov
Most Recent 1 week, 5 days agomengyaoyao
3 weeks, 3 days agoKim222
2 months, 3 weeks agohoomz
9 months agojosephsafiran
10 months agoBamBT
10 months, 3 weeks agomesacgon
11 months agocb4a6c4
11 months, 2 weeks agoJaya12
11 months, 2 weeks agoprinceviper
12 months agosudersonfernando
1 year, 1 month ago