Exam PMP topic 1 question 849 discussion

Actual exam question from PMI's PMP
Question #: 849
Topic #: 1
[All PMP Questions]

A project manager is managing a hybrid project. A stakeholder has directly contacted a team member and has requested a change. Due to the request, the team member was distracted from their work, which caused a loss in productivity

What should the team member do?

  • A. Inform the scrum master so that the change can be discussed directly with the stakeholder.
  • B. Inform the scrum master regarding the stakeholder's request for a change and the impact this has had on productivity
  • C. Inform the stakeholder that the correct procedure for new requirements is to provide it directly to the project manager.
  • D. Inform the stakeholder that the correct procedure for new requirements is to provide it directly to the change control board (CCB).
Show Suggested Answer Hide Answer
Suggested Answer: C 🗳️

Comments

Chosen Answer:
This is a voting comment (?) , you can switch to a simple comment.
Switch to a voting comment New
victory108
Highly Voted 11 months, 2 weeks ago
Selected Answer: B
B. Inform the scrum master regarding the stakeholder's request for a change and the impact this has had on productivity
upvoted 5 times
...
Kim222
Most Recent 2 weeks, 6 days ago
Selected Answer: C
This is C
upvoted 2 times
...
hoomz
7 months ago
Selected Answer: B
While tempting, the team member shouldn't be educating the stakeholder on the process in this manner. This risks coming across as confrontational while the scrum master can handle it professionally.
upvoted 1 times
...
josephsafiran
8 months ago
Selected Answer: C
The team member should **C. Inform the stakeholder that the correct procedure for new requirements is to provide it directly to the project manager**. In a project, especially a hybrid one, it's important to maintain clear lines of communication and follow established procedures for change requests. Directly contacting team members can disrupt their work and lead to miscommunications or misunderstandings. Therefore, stakeholders should direct their requests to the project manager, who can then assess the request and its impact on the project, and decide on the appropriate next steps. This helps to ensure that changes are managed effectively and that team members can focus on their work without unnecessary distractions. It also ensures that all changes are documented and tracked properly.
upvoted 3 times
...
BamBT
8 months, 2 weeks ago
Selected Answer: C
I think the question is asking "What should the team member do IF or WHEN ELSE the stakeholder reach out to the team member". In my opinion, it makes more sense for the team member to refer the stakeholder directly to the PM as this will ensure that the stakeholder know the right thing to do for next time and also resolve the issue of loss of productivity caused by the distraction.
upvoted 3 times
...
mesacgon
9 months ago
Yo voy con B. Recordemos que hay un impacto en la productividad que debe considerarse y que no se soluciona solo con indicar el proceso adecuado de CC.
upvoted 1 times
...
cb4a6c4
9 months, 2 weeks ago
Selected Answer: C
Its a hybrid project, will there be a Scrum Manager? I am confused, can someone pls explain? I choose C though I am confused between C and D.
upvoted 3 times
...
Jaya12
9 months, 2 weeks ago
Selected Answer: C
While options A and B involve informing the scrum master about the stakeholder's request and its impact on productivity, it might not directly address the issue of redirecting the stakeholder to follow the correct procedure for new requirements. Option D, suggesting to inform the stakeholder to provide new requirements directly to the change control board (CCB), might be an excessive step, as typically, new requirements would first go through the project manager for evaluation before reaching the change control board.
upvoted 3 times
...
princeviper
10 months ago
Selected Answer: C
The procedure... 1. Everyone related with the change request can submit to PM. 2. PM then submit the request together with impact analysis to CCB. 3. CCB approves or rejects. Therefore, C is correct.
upvoted 4 times
...
sudersonfernando
11 months, 3 weeks ago
I would go with option B as scrum master serves as a facilitator for the team and can help manage the stakeholder requests
upvoted 3 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...