A member of the project team always extends discussion topics, taking more time than necessary during project team meetings. Other team members feel this member is not being considerate of their time.
What should the project manager do?
A.
Explain to the team that open discussions are needed but remind the team to follow the ground rules.
B.
Ask this member to only discuss the current topic to achieve team efficiency.
C.
Ask the team to accept the input from this particular member as their input may be useful.
D.
Allow the self-organized team to discuss the situation among themselves and come to a resolution.
In this situation, the project manager should take a proactive approach to address the issue and maintain effective team dynamics. The most appropriate action would be:
A. Explain to the team that open discussions are needed but remind the team to follow the ground rules.
By addressing the concern openly with the entire team, the project manager can emphasize the importance of efficient and respectful communication during team meetings. Reminding the team to follow established ground rules ensures that everyone is on the same page and understands the expectations for participation. This approach fosters a positive team environment while also providing guidance on how to manage discussions effectively.
A. Explain to the team that open discussions are needed but remind the team to follow the ground rules
upvoted 1 times
...
This section is not available anymore. Please use the main Exam Page.PMP Exam Questions
Log in to ExamTopics
Sign in:
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.
Upvoting a comment with a selected answer will also increase the vote count towards that answer by one.
So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.
UppersquareCapital
9 months, 3 weeks agoodylec
10 months, 1 week agovictory108
1 year ago