While working on a sprint for a software development project, the team is unsure of how the feature should be designed. The project sponsor recommends developing a prototype of the user interface to discover more about this feature.

Why is the project sponsor making this suggestion?

  • A. The information gathered will help the team improve the allocation of resources in developing the most important features.
  • B. The project sponsor believes that the agile team is not adding in the most important features during this sprint.
  • C. The users can help the team understand if the feature adds value, avoiding the risk of building the wrong product.
  • D. The users will start using the software sooner, and the team can start working on the next iteration.
Show Suggested Answer Hide Answer
Suggested Answer: C 🗳️

Comments

Chosen Answer:
This is a voting comment (?) , you can switch to a simple comment.
Switch to a voting comment New
thewalker
2 weeks, 1 day ago
Selected Answer: C
The project sponsor is suggesting a prototype to gather user feedback and validate that the feature being developed will meet user needs. This approach allows the team to avoid the risk of building a feature that might not provide the expected value or might be designed incorrectly.
upvoted 1 times
thewalker
2 weeks, 1 day ago
A. The information gathered will help the team improve the allocation of resources in developing the most important features. While prototyping can help identify feature priorities, the primary reason for prototyping in this case is to validate user needs and avoid building something that might not be useful. B. The project sponsor believes that the agile team is not adding in the most important features during this sprint. There's no mention that the sponsor believes the team is focusing on the wrong features. The prototype is suggested to clarify the design and ensure it aligns with user expectations. D. The users will start using the software sooner, and the team can start working on the next iteration. The primary goal of the prototype isn't to get the software in users' hands faster but to validate the feature and gather insights that will influence its design and development.
upvoted 1 times
...
...
PuranDom
1 month ago
yes C is the best. why not A, B and D are as follows, A: not talking about resource issue B: may seem like candidate but not touching about customer collaboration. C is even better . D: seems like user will utilize mockup (working software) but nothing mentioned about how to gather correct requirements. So this is not right option
upvoted 1 times
...
Tonome
9 months, 4 weeks ago
So instead of creatingvery detailed specifications andplans, agileprojects build aprototype to better understand the domain anduse thisprototype as thebasis for furtherplanningand elaboration. C
upvoted 2 times
...
Petrevski
1 year ago
Selected Answer: C
C = correct
upvoted 2 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...