An organization is initiating a project that will be using new technology. The complexity of the project requires excellent technical skills. After reviewing the proposed project management plan, the project sponsor asks for options to reduce the labor cost without introducing risk to the project delivery.

What should the project manager do first?

  • A. Review the risk register and assign functional managers as resources.
  • B. Perform an analysis of the key cost drivers and present alternatives.
  • C. Analyze the resource pool and assign internal resources who participated in past projects.
  • D. Review the work breakdown structure (WBS) to ensure there are adequate resources.
Show Suggested Answer Hide Answer
Suggested Answer: B 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
UA_86
2 weeks, 2 days ago
Selected Answer: B
Option B is best in the case.
upvoted 1 times
...
victory108
9 months ago
Selected Answer: B
B. Perform an analysis of the key cost drivers and present alternatives
upvoted 2 times
...
kayyaly
9 months, 2 weeks ago
Selected Answer: B
B. Perform an analysis of the key cost drivers and present alternatives.
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...
exam
Someone Bought Contributor Access for:
SY0-701
London, 1 minute ago