An organization is initiating a project that will be using new technology. The complexity of the project requires excellent technical skills. After reviewing the proposed project management plan, the project sponsor asks for options to reduce the labor cost without introducing risk to the project delivery.
What should the project manager do first?
UA_86
2 weeks, 2 days agovictory108
9 months agokayyaly
9 months, 2 weeks ago