Midway through the execution of an agile protect there is a shift in the strategic objectives at the organization level to promote digital transformation. What should the project manager do next?
A.
Schedule a meeting with the team to assess the impact of the change
B.
Escalate to the product owner and cancel the upcoming iterations
C.
Prepare a user story to handle the change and assign it to the next iteration
D.
Update the risk-prioritized backlog with the strategic change
This section is not available anymore. Please use the main Exam Page.PMP Exam Questions
Log in to ExamTopics
Sign in:
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.
Upvoting a comment with a selected answer will also increase the vote count towards that answer by one.
So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.
00c83c8
1 week, 6 days agovictory108
6 months, 2 weeks agokayyaly
7 months ago