exam questions

Exam PMP All Questions

View all questions & answers for the PMP exam

Exam PMP topic 1 question 584 discussion

Actual exam question from PMI's PMP
Question #: 584
Topic #: 1
[All PMP Questions]

A project manager accepts a delivery at the project site but the items are of a poor quality. The project manager gets the local vendor to fix the items but more deliveries from this vendor are expected.
What should the project manager do going forward?

  • A. Allocate extra time to inspect deliveries for quality assurance upon arrival at the site
  • B. Review the contract requirements and ask for the applicable evidence for quality assurance
  • C. Have the vendor issue the quality documentation prior to the next delivery
  • D. Call the vendor and have them verbally guarantee the quality of the next site delivery
Show Suggested Answer Hide Answer
Suggested Answer: B 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
kayyaly
7 months, 3 weeks ago
Selected Answer: B
B. Review the contract requirements and ask for the applicable evidence for quality assurance
upvoted 1 times
...
victory108
7 months, 3 weeks ago
Selected Answer: B
B. Review the contract requirements and ask for the applicable evidence for quality assurance
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...
exam
Someone Bought Contributor Access for:
SY0-701
London, 1 minute ago