Welcome to ExamTopics
ExamTopics Logo
- Expert Verified, Online, Free.
exam questions

Exam PMP All Questions

View all questions & answers for the PMP exam

Exam PMP topic 1 question 843 discussion

Actual exam question from PMI's PMP
Question #: 843
Topic #: 1
[All PMP Questions]

A project manager is in a team meeting and the project team requires a decision to be made about a new suggested timeline due to an impact from a potential scope change. What should the project manager do?

  • A. Follow the stakeholder engagement plan.
  • B. Review the stakeholder map along with the organizational chart and delegate the most senior person to make the decision.
  • C. Schedule a project decision meeting with all stakeholders to discuss the decision.
  • D. Make the decision on behalf of the organization.
Show Suggested Answer Hide Answer
Suggested Answer: A 🗳️

Comments

Chosen Answer:
This is a voting comment (?) , you can switch to a simple comment.
Switch to a voting comment New
23169fd
1 month, 2 weeks ago
Selected Answer: A
The stakeholder engagement plan is designed to outline how decisions are made, who is responsible, and the appropriate level of involvement for each stakeholder. It provides a framework for decision-making that ensures the right stakeholders are involved, based on their roles, influence, and responsibilities in the project. By following the stakeholder engagement plan, the project manager ensures that the decision is made in alignment with the agreed-upon governance and with the appropriate input from relevant stakeholders, ensuring a balanced and informed decision.
upvoted 1 times
...
LNX_RM_Admin
6 months, 2 weeks ago
Selected Answer: C
By scheduling a project decision meeting with all stakeholders, the project manager ensures that key decision-makers are involved in the discussion and have the opportunity to provide input and consider the implications of the proposed timeline change. This approach promotes transparency, collaboration, and buy-in from stakeholders, which are essential for effective decision-making and successful project outcomes.
upvoted 2 times
...
buvana
8 months, 1 week ago
C. Schedule a project decision meeting with all stakeholders to discuss the decision.
upvoted 2 times
...
Abdelmonm
10 months, 1 week ago
Selected Answer: C
In a situation where a decision needs to be made about a new suggested timeline due to a potential scope change, it's essential to involve relevant stakeholders in the decision-making process. Scheduling a project decision meeting with all stakeholders allows for a collaborative discussion. This approach ensures that different perspectives are considered, and decisions are made collectively. Following the stakeholder engagement plan and involving key stakeholders aligns with best practices in project management.
upvoted 2 times
...
xcjxcj
10 months, 1 week ago
Selected Answer: A
Decision is needed A. Let's see who B. Oldest one decide C. Let us all decide D. I decide A seems correct (relevant people should decide)
upvoted 3 times
...
chlaithem
10 months, 2 weeks ago
Selected Answer: C
This option emphasizes inclusivity, transparency, and collective responsibility. By scheduling a dedicated meeting with stakeholders: Comprehensive discussion: The project manager can present the situation, potential impacts of the new timeline, and any available alternatives. Stakeholders can voice their concerns, ask questions, and share their perspectives. Informed decision: Through open discussion and analysis, the project manager can gather valuable insights and consider all angles before making a final decision aligned with project goals and stakeholder priorities. Shared ownership: Engaging stakeholders in the decision-making process fosters team unity and acceptance of the chosen path, promoting future collaboration and commitment.
upvoted 2 times
...
Only12go
1 year, 1 month ago
Selected Answer: A
option A, "Follow the stakeholder engagement plan," provides a structured, agreed-upon approach to address such situations. The plan would have guidelines and procedures for how decisions like these should be approached, ensuring consistency and adherence to project governance.
upvoted 3 times
...
sudersonfernando
1 year, 1 month ago
I would go with option C as it promotes transparency in the decision making process by involving stakeholders
upvoted 1 times
David983
1 year, 1 month ago
Not ALL the stakeholders need to be involved in the decition like Option C said. It´s more accurate the option A that suggest "Follow the stakeholder engagement plan" in order to involve them on different levels according to each stakeholders characteristics
upvoted 2 times
...
...
SynikalDemon
1 year, 2 months ago
A - I almost went with another answer, but yeah is probably right.
upvoted 3 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...