Welcome to ExamTopics
ExamTopics Logo
- Expert Verified, Online, Free.
exam questions

Exam PMP All Questions

View all questions & answers for the PMP exam

Exam PMP topic 1 question 818 discussion

Actual exam question from PMI's PMP
Question #: 818
Topic #: 1
[All PMP Questions]

A business analyst on the project meets the customer in the elevator and says that due to constant changes in requirements, the development of the product will take more time than expected. What should the project manager do?

  • A. Submit a change request to the change control board (CCB) in order to reflect the new requirements and longer timeline of the project.
  • B. Point out to the project team and the customer that all information concerning the timeline of the project should be communicated by the project manager.
  • C. Refer to the resource management plan to find out if more business analysts may be assigned to process the requirements changes.
  • D. Explain that distribution of important news can only be done using traceable communication methods.
Show Suggested Answer Hide Answer
Suggested Answer: D 🗳️

Comments

Chosen Answer:
This is a voting comment (?) , you can switch to a simple comment.
Switch to a voting comment New
d370e49
1 week, 2 days ago
Selected Answer: D
It's clearly D. The word "Explain" is a softer and more orderly way to proceed than they others. This is actually a question of Emotional Intelligence.
upvoted 1 times
...
Abdelmonm
8 months, 1 week ago
Selected Answer: B
In this scenario, it's essential to emphasize proper communication channels and the role of the project manager in conveying information about the project timeline. The project manager is responsible for managing project communications and ensuring that all stakeholders are informed through official and traceable communication methods. This helps maintain transparency, accountability, and a structured approach to handling project-related information. If there are changes to the timeline, they should be communicated through established channels, such as change requests, to ensure proper documentation and governance.
upvoted 1 times
...
chlaithem
8 months, 1 week ago
Selected Answer: B
This option addresses the unauthorized communication and reinforces appropriate procedures. By communicating to both the team and the customer, the project manager: Clarifies that project timeline updates should be communicated officially through designated channels. Reasserts project communication hierarchy and protocol, maintaining control over sensitive information. Rebuilds trust and transparency by addressing the miscommunication directly.
upvoted 1 times
...
cb4a6c4
9 months, 2 weeks ago
Selected Answer: A
Submit a change and let the CCB approve or reject the change.
upvoted 1 times
...
Only12go
11 months ago
Selected Answer: B
B. Point out to the project team and the customer that all information concerning the timeline of the project should be communicated by the project manager. In this situation, it's important to reinforce the project communication protocols and clarify that any information regarding project timelines and changes should be communicated through the project manager. This helps maintain a structured and controlled communication process within the project. While option A mentions submitting a change request, this may not be necessary if the business analyst's comment is more about providing information rather than requesting a formal change in project scope or timeline. Option B focuses on maintaining proper communication channels and project management responsibilities.
upvoted 1 times
...
victory108
11 months, 2 weeks ago
Selected Answer: B
B. Point out to the project team and the customer that all information concerning the timeline of the project should be communicated by the project manager
upvoted 1 times
...
SynikalDemon
1 year ago
Selected Answer: B
Anything concerning the timeline should come from the Project Manager.
upvoted 2 times
...
Inzaghi78
1 year ago
Selected Answer: A
A need to submit change resquest to formalize
upvoted 3 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...