Welcome to ExamTopics
ExamTopics Logo
- Expert Verified, Online, Free.
exam questions

Exam PMI-ACP All Questions

View all questions & answers for the PMI-ACP exam

Exam PMI-ACP topic 1 question 320 discussion

Actual exam question from PMI's PMI-ACP
Question #: 320
Topic #: 1
[All PMI-ACP Questions]

The product owner is very concerned about work not being completed and tested before a hard release date. What can the agile team do to mitigate this risk?

  • A. High-risk features can be prioritized to fit into releases with less work in progress.
  • B. Low-risk, low-value features can be prioritized and completed first.
  • C. High-risk, low-value features can be evaluated by the team early in the release.
  • D. The work in progress can be adjusted to get more reviews with high-risk features.
Show Suggested Answer Hide Answer
Suggested Answer: A 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
thewalker
2 months, 2 weeks ago
Selected Answer: A
Prioritizing high-risk features early ensures that the most critical and complex work is addressed first, reducing the chances of encountering major issues close to the release date. By focusing on these features while maintaining less work in progress, the team can ensure better focus, reduce bottlenecks, and allocate enough time for testing and validation, mitigating the risk of incomplete work before the hard release deadline. Other options: B: Prioritizing low-risk, low-value features doesn’t address the concern of risk and time constraints. C: High-risk, low-value features may not provide significant value even if they are risky, so prioritizing them doesn't necessarily mitigate overall project risk. D: Adjusting work in progress for more reviews might help, but focusing on high-risk features directly tackles the product owner's concern more effectively.
upvoted 1 times
...
Nervys
1 year ago
D is correct
upvoted 1 times
...
Petrevski
1 year, 2 months ago
Selected Answer: A
A = correct
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...