Welcome to ExamTopics
ExamTopics Logo
- Expert Verified, Online, Free.
exam questions

Exam PMI-ACP All Questions

View all questions & answers for the PMI-ACP exam

Exam PMI-ACP topic 1 question 306 discussion

Actual exam question from PMI's PMI-ACP
Question #: 306
Topic #: 1
[All PMI-ACP Questions]

A software company is developing an accounting software system to market to customers. The team has been working on the project for six weeks and has great velocity. One of the major stakeholders approached the scrum master and asked for a bi-weekly status report because they feel they are not being properly updated.

How should the scrum master respond to this request?

  • A. Inform the stakeholder that all updates are provided in the sprint review sessions and encourage them to attend.
  • B. Create and update bi-weekly project status reports for the stakeholder who requested the report.
  • C. Escalate this to the stakeholder's supervisor because this is an unreasonable request.
  • D. Ignore the stakeholder's request and continue working on the project as they have been for the past six weeks.
Show Suggested Answer Hide Answer
Suggested Answer: A 🗳️

Comments

Chosen Answer:
This is a voting comment (?) , you can switch to a simple comment.
Switch to a voting comment New
thewalker
1 week, 5 days ago
Selected Answer: A
In Scrum, the primary mechanism for stakeholder updates is the sprint review session, where the team demonstrates the work completed during the sprint and discusses progress. By encouraging the stakeholder to attend these reviews, the Scrum Master ensures that the stakeholder gets the most current and relevant updates in a format consistent with Agile practices. Other options are less appropriate because: B: Creating and updating bi-weekly project status reports adds additional overhead and may not align with Agile principles of minimal documentation and maximizing face-to-face communication. C: Escalating the request may be premature and does not address the stakeholder's need for information directly or constructively. D: Ignoring the request does not address the stakeholder's concerns and could lead to misunderstandings or dissatisfaction.
upvoted 1 times
...
Nervys
10 months, 1 week ago
"A" for sure
upvoted 1 times
...
Petrevski
1 year ago
Selected Answer: A
A = correct
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...