Exam PMI-ACP topic 1 question 294 discussion

Actual exam question from PMI's PMI-ACP
Question #: 294
Topic #: 1
[All PMI-ACP Questions]

The team is aware that they will need to integrate a new component to their solution in the next few weeks. The team does not have any experience with this component.

What should the team do next?

  • A. Ask for a team extension so that an engineer with the needed experience can be added to the team.
  • B. Suggest that the product owner perform the initial investigation and present the outcome to the team.
  • C. Request that the product owner include a spike in the next iteration's backlog so they can perform an initial investigation.
  • D. Propose alternative components with which the team has experience.
Show Suggested Answer Hide Answer
Suggested Answer: C 🗳️

Comments

Chosen Answer:
This is a voting comment (?) , you can switch to a simple comment.
Switch to a voting comment New
yassoraa88
3 months ago
Selected Answer: C
C is correct
upvoted 2 times
...
Petrevski
1 year, 2 months ago
Selected Answer: C
C = correct
upvoted 2 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...