Exam PMP topic 1 question 842 discussion

Actual exam question from PMI's PMP
Question #: 842
Topic #: 1
[All PMP Questions]

An agile team is working on a two-week sprint to deliver business value. About one week after the sprint starts, the product owner realizes that a regulatory compliance requirement was missed. The product owner reminds the team that this requirement must be completed in the current sprint or the organization will face a penalty.

What should the project manager do to mitigate this risk?

  • A. Review the issue with the project sponsor and ask for more time to complete this requirement.
  • B. Complete an impact analysis as the scope of the sprint backlog cannot be changed after the sprint has started.
  • C. Include the compliance user story in the next sprint as the team is fully occupied with the current sprint.
  • D. Request the team to add the user story to the current sprint and let them work on it.
Show Suggested Answer Hide Answer
Suggested Answer: D 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
Abdelmonm
Highly Voted 10 months, 1 week ago
Selected Answer: B
In Agile methodologies, the principle of maintaining the integrity of the sprint backlog is crucial. Once a sprint has started, the scope is typically fixed to provide a stable environment for the development team to work and deliver on their commitments. Therefore, the project manager should conduct an impact analysis to assess the consequences of introducing the compliance requirement into the current sprint. This analysis should consider factors such as the team's capacity, the potential impact on existing commitments, and the likelihood of meeting the sprint goals. If the impact analysis suggests that adding the compliance requirement is feasible without significantly disrupting the sprint, the team may choose to incorporate it. However, this decision should be made collaboratively with the team, and the product owner should be involved in prioritizing the work within the sprint backlog.
upvoted 6 times
...
Kim222
Most Recent 2 months, 3 weeks ago
Selected Answer: B
This is B
upvoted 1 times
...
tonybuivannghia
3 months, 4 weeks ago
Selected Answer: D
D seems rights.
upvoted 2 times
...
UppersquareCapital
6 months, 1 week ago
Selected Answer: D
Regulatory compliance is critical and often takes precedence over other tasks due to the legal and financial implications of non-compliance. Ignoring this requirement could lead to penalties, making it essential to address it immediately. While it is generally advised to avoid changing the sprint backlog once a sprint has started, agile methodologies also emphasize responding to change over following a plan. When new, critical information arises, such as a missed compliance requirement, the team must be flexible enough to adapt. Agile teams are self-organizing and empowered to manage their work. The project manager can request the team to assess the situation and decide how to incorporate the compliance requirement into the current sprint. The team can reprioritize their tasks to accommodate this high-priority item.
upvoted 3 times
...
LNX_RM_Admin
6 months, 2 weeks ago
Selected Answer: D
Since the regulatory compliance requirement is critical and missing it would lead to penalties for the organization, it should be addressed as soon as possible
upvoted 2 times
...
debug91
6 months, 3 weeks ago
Selected Answer: B
B 맞습니다
upvoted 1 times
...
[Removed]
9 months ago
Selected Answer: D
The impact is already clear, we don't need a analysis. So D would be the best answer.
upvoted 2 times
...
hoomz
9 months, 1 week ago
Selected Answer: B
In agile methodologies like Scrum, changing the sprint backlog mid-sprint undermines the core idea of time-boxed iterations. This allows the team to focus, avoid scope creep, and get better at estimating work within a defined timeframe.
upvoted 3 times
...
chlaithem
10 months, 2 weeks ago
Selected Answer: D
This option emphasizes immediate action and team collaboration. By: Involving the team: The project manager can explain the missed compliance requirement and its potential consequences. Adding the user story to the current sprint backlog: The team can prioritize and discuss how to potentially integrate the new user story while managing existing commitments. Empowering the team to choose their workload: Allowing the team to assess their capacity and adapt their workplan demonstrates trust and encourages collaboration in finding solutions.
upvoted 1 times
...
David983
1 year, 1 month ago
Selected Answer: D
Option B is not right, the Sprint Backlog can be changed after started if the Project Team accept the change with the corresponding arguments
upvoted 4 times
...
Only12go
1 year, 1 month ago
Selected Answer: D
Considering the penalty for not addressing the compliance requirement in the current sprint, the best approach would be: D. Request the team to add the user story to the current sprint and let them work on it. While it's generally not advisable to change the sprint backlog once it's started in Agile, the urgency of the compliance requirement and the potential penalty may justify making an exception in this case. The project manager should discuss this with the team and product owner to ensure they can accommodate the additional work within the current sprint without compromising the sprint goal. This approach addresses the immediate risk of the penalty and allows the team to remain compliant. However, it should be done with careful consideration and collaboration with the team to avoid overburdening them.
upvoted 3 times
...
Sumbo
1 year, 1 month ago
D is the right Answer, why are we agile if we cannot pivot..
upvoted 1 times
...
AngelVii
1 year, 2 months ago
i think the right answer is D
upvoted 1 times
...
SynikalDemon
1 year, 2 months ago
D seems right. As this MUST be completed this sprint.
upvoted 1 times
...
khaleghi
1 year, 3 months ago
Selected Answer: D
D. Request the team to add the user story to the current sprint and let them work on it.
upvoted 2 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.