An agile team is working on a two-week sprint to deliver business value. About one week after the sprint starts, the product owner realizes that a regulatory compliance requirement was missed. The product owner reminds the team that this requirement must be completed in the current sprint or the organization will face a penalty.
What should the project manager do to mitigate this risk?
Abdelmonm
Highly Voted 1 year agoKim222
Most Recent 5 months, 2 weeks agotonybuivannghia
6 months, 3 weeks agoUppersquareCapital
9 months agoLNX_RM_Admin
9 months, 1 week agodebug91
9 months, 2 weeks ago[Removed]
11 months, 3 weeks agohoomz
12 months agochlaithem
1 year, 1 month agoDavid983
1 year, 3 months agoOnly12go
1 year, 3 months agoSumbo
1 year, 4 months agoAngelVii
1 year, 5 months agoSynikalDemon
1 year, 5 months agokhaleghi
1 year, 5 months ago