An agile team is working on a two-week sprint to deliver business value. About one week after the sprint starts, the product owner realizes that a regulatory compliance requirement was missed. The product owner reminds the team that this requirement must be completed in the current sprint or the organization will face a penalty.
What should the project manager do to mitigate this risk?
Abdelmonm
Highly Voted 8 months agoKim222
Most Recent 2 weeks, 6 days agotonybuivannghia
1 month, 3 weeks agoUppersquareCapital
4 months agoLNX_RM_Admin
4 months, 1 week agodebug91
4 months, 2 weeks ago[Removed]
6 months, 3 weeks agohoomz
7 months agochlaithem
8 months, 2 weeks agoDavid983
11 months agoOnly12go
11 months agoSumbo
11 months, 2 weeks agoAngelVii
1 year agoSynikalDemon
1 year agokhaleghi
1 year ago