Question #: 834
Topic #: 1
[All PMP Questions]

During the early phases of a project, mitigation actions were not executed in a timely manner; therefore, the project schedule was impacted. Several project stakeholders are now frustrated with the delays.

What should the project manager have done to manage the issue?

  • A. Identified and reported the issue
  • B. Monitored and controlled the issue
  • C. Identified the appropriate response and had it implemented
  • D. Communicated any identified action to impacted stakeholders
Show Suggested Answer Hide Answer
Suggested Answer: D 🗳️

Comments

Chosen Answer:
This is a voting comment (?) , you can switch to a simple comment.
Switch to a voting comment New
Kim222
2 weeks, 6 days ago
Selected Answer: C
This is C
upvoted 1 times
...
[Removed]
6 months, 3 weeks ago
Selected Answer: B
B, because the risk response was not executed in a timely manner
upvoted 1 times
...
rshankhwa
7 months, 2 weeks ago
Selected Answer: B
Would go with B. Mitigation actions were not executed in a timely manner. This means mitigations actions were done but not on timely manner. So the Risks should have been monitored correctly and based on the outcome and impact mitigation should have been done on timely manner. C says - Identified the appropriate response. It never said in the scenario that response was applied inappropriately so cannot be an option
upvoted 4 times
...
Abdelmonm
8 months, 1 week ago
Selected Answer: C
In project management, when issues or risks are identified, it is crucial to not only report them but also to take appropriate actions to address or mitigate them. The correct course of action is to identify the appropriate response or mitigation plan and ensure that it is implemented in a timely manner. This proactive approach helps in minimizing the impact of issues on the project schedule and preventing further delays. Additionally, effective communication with stakeholders about the identified actions and their implementation is essential to manage expectations and maintain transparency throughout the project.
upvoted 2 times
...
kevzzz
8 months, 1 week ago
Selected Answer: C
Mitigation is risk. What are the four risk mitigation strategies? There are four common risk mitigation strategies: avoidance, reduction, transference, and acceptance.
upvoted 2 times
...
BamBT
8 months, 2 weeks ago
Selected Answer: B
B: Monitoring & Controlling the issue The question states that "mitigation actions were not executed in a timely manner", I will assume that at some point, the project manager had carried out option: "C: Identified the appropriate response and had it implemented" but not in a timely manner which leaves room to say the PM might have not taking a close look during the Monitoring and Controlling phase of the project leaving option "C: Identified the appropriate response and had it implemented" for the very last minute which might lead to the project stakeholders frustration and the delay of the project.
upvoted 3 times
...
mesacgon
9 months ago
Debería ser B. El PM no es responsable de implementar la respuesta a las mitigaciones.
upvoted 1 times
...
odylec
9 months ago
Selected Answer: C
C is the answer
upvoted 1 times
...
David983
10 months, 3 weeks ago
Selected Answer: D
The correct Option is D, Mitigation Action Owners are the different stakeholders and not just the PM, PM is the owner to communicate the actions and ensure it carried out properly and timely
upvoted 1 times
...
Only12go
11 months ago
Selected Answer: C
The correct answer is C. "Identified the appropriate response and had it implemented." Given the situation, where mitigation actions were not executed in a timely manner, it suggests that while the risks might have been identified, the proper responses were not promptly implemented. It's essential for the project manager to not just identify risks, but also to define and carry out the appropriate responses to manage those risks effectively. This would have likely prevented the schedule impact and subsequent stakeholder frustration.
upvoted 3 times
...
victory108
11 months, 2 weeks ago
Selected Answer: C
C. Identified the appropriate response and had it implemented
upvoted 2 times
...
adingmaki
11 months, 2 weeks ago
I think C as well
upvoted 1 times
...
AngelVii
1 year ago
Selected Answer: C
I feel C is the right answer in the exam
upvoted 2 times
...
SynikalDemon
1 year ago
C - The key word is mitigated. We mitigate, RISK. The question is about risk. The proper risk response would have prevented this situation.
upvoted 1 times
...
khaleghi
1 year ago
Selected Answer: C
answer is C.
upvoted 2 times
prjmanager
1 year ago
But the issue pertains to time constraints rather than deficiencies in the actions.I think B would be the appropriate answer.
upvoted 4 times
...
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...