Welcome to ExamTopics
ExamTopics Logo
- Expert Verified, Online, Free.
exam questions

Exam PMP All Questions

View all questions & answers for the PMP exam

Exam PMP topic 1 question 815 discussion

Actual exam question from PMI's PMP
Question #: 815
Topic #: 1
[All PMP Questions]

A project manager has experience working with a specific provider that has been requested for an upcoming project. This provider often fails to meet deliverable dates; however it is the only company with the specific experience required for the project.

What should the project manager do during the planning phase?

  • A. Encourage the provider to work overtime with no additional costs to the project.
  • B. Hire resources to obtain knowledge about the provider's specific capabilities.
  • C. Add penalty clauses to the contract and update the risk register.
  • D. Contract another provider with less experience and give them a chance to provide the deliverables.
Show Suggested Answer Hide Answer
Suggested Answer: A 🗳️

Comments

Chosen Answer:
This is a voting comment (?) , you can switch to a simple comment.
Switch to a voting comment New
Kim222
2 weeks, 6 days ago
Selected Answer: C
C is alright
upvoted 1 times
...
9RedFox_JB
4 months, 1 week ago
I would also go with the C. but I did had a case that provider was constantly delaying his deliverables, and we did proposed for them that if they not delivering what they promised they should cover needed effort on their side or mare more realistic assumptions. at that moment it seemed good approach, because we knew the provider and we where in a good relationship. penalties would would have seemed as a unpleasant punishment.
upvoted 1 times
...
JeffLesz
7 months, 4 weeks ago
Selected Answer: C
once again, the system says something that morally doesn't sound right. How can you ask (TELL) a company, even if it has messed up in the past, that it needs to work unpaid overtime? You'd think that if your Lesson Learned is that consistently this contractor does not provide the correct quoted equipment, and thus causes delay, that they would build that Lag time into a project plan, but not sure how it would go over at the other company...i'd ask for legal advise, and agree with the other answer every agrees to, add the penalty fees and update the risk register.
upvoted 1 times
dimo475
6 months, 3 weeks ago
We have to be careful here. The answer A doesn't say anything about unpaid overtime but "overtime without additional cost to the project" which is not the same thing. That's why *A* is the right answer, it is a collaborative step prior to the penalties which can cause the loss of the valuable contractor.
upvoted 1 times
...
...
Abdelmonm
8 months, 1 week ago
Selected Answer: C
In this situation, adding penalty clauses to the contract is a proactive measure to address the provider's historical issue of failing to meet deliverable dates. Penalty clauses can create accountability and provide a financial incentive for the provider to meet the specified deadlines. This approach helps mitigate the risk associated with the provider's past performance. Additionally, updating the risk register is crucial to document the identified risk, the chosen mitigation strategy (penalty clauses), and any other relevant information. This ensures that the project manager and the team are aware of the risk and the planned response, facilitating effective risk management throughout the project.
upvoted 1 times
...
chlaithem
8 months, 2 weeks ago
Selected Answer: C
This option focuses on contractual protection and managing potential delays. By incorporating penalty clauses: You incentivize the provider to adhere to deadlines by imposing financial consequences for missed deliverables. You provide leverage for negotiating extensions or seeking compensation if deadlines are not met. Updating the risk register ensures proactive identification and mitigation strategies for identified risks, including potential delays from the chosen provider. You can: Analyze the specific reasons for past missed deadlines and develop contingency plans to address them (e.g., increased communication, milestones, progress checks). Consider alternative solutions or backup plans in case delays become inevitable.
upvoted 1 times
...
Waynelau
9 months ago
Selected Answer: C
Working overtime may not be legal in some countries, so encourage vendor work overtime may not be a possible solution. So C should be the correct answer.
upvoted 1 times
...
Only12go
11 months ago
Selected Answer: C
C. Add penalty clauses to the contract and update the risk register. Given the provider's history of not meeting deliverable dates, it would be prudent for the project manager to anticipate potential delays. Adding penalty clauses to the contract can serve as a deterrent for the provider, encouraging them to adhere to timelines. Additionally, updating the risk register will ensure that the project team is aware of the potential risk and can plan accordingly.
upvoted 2 times
...
Joelush
11 months, 2 weeks ago
C for me
upvoted 1 times
...
victory108
11 months, 2 weeks ago
Selected Answer: C
C. Add penalty clauses to the contract and update the risk register
upvoted 1 times
...
IykeNw
11 months, 4 weeks ago
Selected Answer: C
It's C
upvoted 1 times
...
SynikalDemon
1 year ago
Selected Answer: C
It's C.
upvoted 1 times
...
Inzaghi78
1 year ago
Selected Answer: C
add penalty to encourage the vender to produce good quality
upvoted 1 times
...
khaleghi
1 year ago
Selected Answer: C
C. Add penalty clauses to the contract and update the risk register.
upvoted 2 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...