Welcome to ExamTopics
ExamTopics Logo
- Expert Verified, Online, Free.
exam questions

Exam PMI-ACP All Questions

View all questions & answers for the PMI-ACP exam

Exam PMI-ACP topic 1 question 286 discussion

Actual exam question from PMI's PMI-ACP
Question #: 286
Topic #: 1
[All PMI-ACP Questions]

A project's product owner asks the scrum master to facilitate the estimation activity. The scrum master then meets with the team and the product owner to clarify the user stories. Following the meeting, the team assembles and provides individual user-story estimates.

What technique did the team use?

  • A. Lessons learned
  • B. Wideband Delphi
  • C. Formal point counting
  • D. Planning poker
Show Suggested Answer Hide Answer
Suggested Answer: D 🗳️

Comments

Chosen Answer:
This is a voting comment (?) , you can switch to a simple comment.
Switch to a voting comment New
thewalker
1 week, 5 days ago
Selected Answer: D
Planning poker is a consensus-based estimation technique used in agile projects. It involves team members providing individual estimates for user stories after a discussion to clarify the requirements. The process typically includes the following steps: The product owner presents a user story to the team. Team members discuss the story to ensure a shared understanding. Each team member privately selects an estimate (usually a card with a number representing story points). All estimates are revealed simultaneously. If there is a significant variance in estimates, the team discusses the differences and re-estimates until a consensus is reached.
upvoted 1 times
thewalker
1 week, 5 days ago
A. Lessons learned: This refers to reviewing past projects or sprints to capture insights and improve future performance. It's not an estimation technique. B. Wideband Delphi: This is a group estimation method where experts give their estimates anonymously, and rounds of discussions and reviews are conducted to reach consensus. It’s more formal and usually does not involve open discussion after each round like planning poker. C. Formal point counting: This refers to a specific method like function point analysis, which is more common in traditional software engineering and less interactive than the Agile process described.
upvoted 1 times
...
...
patti13
9 months, 2 weeks ago
D is correct
upvoted 1 times
...
Petrevski
1 year ago
Selected Answer: D
D = correct
upvoted 2 times
Petrevski
1 year ago
Wideband Delphi = consensus-based estimation Planning Poker = individual-based estimation
upvoted 2 times
...
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...