A project manager is leading a project in an organization that has a functional structure. The project manager has been informed by the team that the tasks related to the purchase of services are taking too long, as the purchasing department has other priorities.

What should the project manager do?

  • A. Ask the project team to keep developing other tasks that do not depend on the purchase of services.
  • B. Meet with the purchasing manager to find the source of the delays and agree on a purchasing schedule.
  • C. Request that the purchasing tasks be outsourced through an existing purchasing vendor.
  • D. Modify the project schedule to accommodate the delays in the purchase of services.
Show Suggested Answer Hide Answer
Suggested Answer: B 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
6thEditionAndy
3 weeks, 1 day ago
Selected Answer: B
Theoretically B, but the larger the company, the less this applies in real life.
upvoted 1 times
...
victory108
2 months, 3 weeks ago
Selected Answer: B
B. Meet with the purchasing manager to find the source of the delays and agree on a purchasing schedule
upvoted 1 times
...
Jamrock
3 months, 3 weeks ago
Selected Answer: B
stresses collaboration
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...
exam
Someone Bought Contributor Access for:
SY0-701
London, 1 minute ago